Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

Commencement notice

AED 39
Launch offerAED 19.50 on your first order, until 31 December.
EngineerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 8.1
Time limit
Not less than 7 days’ notice of the Commencement Date
Format
Word, 3 pagesEnglish and Arabic copy, 3 pages
Stage
Post-contract: 3. Sign and startRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • The Engineer’s notice fixing the date from which the Time for Completion runs.
  • Sent by the Engineer to the Main Contractor.
  • Written to FIDIC 1999 Red Book, Sub-Clause 8.1.
  • Time limit: Not less than 7 days’ notice of the Commencement Date.

What you get

Save with a pack

Engineer to Main Contractor: Sign and start4 documents. Includes this document.
AED 176AED 109Save AED 67

Free basic version or the full version

Free

Basic version

  • The English Word form, 3 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 39

  • The same Word form, with no line in the footer
  • English and Arabic copy, 3 pages
  • Your logo and company details on every file
How to write it

How to give notice of the Commencement Date

The commencement notice fixes the date from which the Time for Completion runs. Under Sub-Clause 8.1 of the FIDIC 1999 Red Book, the Engineer gives the Contractor at least 7 days’ notice of the Commencement Date, which falls within 42 days after the Contractor receives the Letter of Acceptance unless the Particular Conditions say otherwise.

What to include

  1. 1The contract name and number
  2. 2The Commencement Date, at least 7 days after the notice
  3. 3The Time for Completion, and the completion date that follows, for the Works and each Section
  4. 4When the programme is due: within 28 days after the notice (Sub-Clause 8.3)
  5. 5When and how access to the Site will be given
  6. 6The status of the Performance Security, and the Contractor’s Representative
  7. 7The kick-off meeting, and a request to acknowledge

When to use it

After the Letter of Acceptance, at least 7 days before the Commencement Date. The Contractor then starts as soon as reasonably practicable after that date and proceeds with due expedition and without delay.

Read the full guideClear to pay: the checklist before the first payment
Sample wording
Under Sub-Clause 8.1 we give notice that the Commencement Date of the Works is 1 April 2026. The Time for Completion is 730 days, so the Works are to be completed by 31 March 2028. Please submit the programme under Sub-Clause 8.3 within 28 days after receiving this notice.

Common mistakes

  • Giving less than 7 days’ notice
  • No completion date stated, which leads to arguments later
  • Fixing a Commencement Date before the Site can be accessed

Questions people ask

When does the Time for Completion start?

On the Commencement Date stated in the notice, not on the date of the Letter of Acceptance or of the Contract Agreement.

What if the Site is not ready on the Commencement Date?

If the Employer fails to give access in time, the Contractor may claim an extension of time and Cost plus reasonable profit under Sub-Clause 2.1, after giving notice under Sub-Clause 20.1.