FIDIC claim deadline calculator
Enter the date you became aware of the event and see every claim deadline under your contract form, with the days left. Add the dates to your calendar, or get an email reminder 7 days before each one.
Or the date you should have become aware of it.
Fully detailed claim
Sub-Clause 20.1, or another period the Engineer approves.
Use the template: Fully detailed extension of time and prolongation claimEngineer’s response
Within 42 days after it receives your fully detailed claim (shown here if you send it on the last day).
Use the template: Engineer’s response to notice and request for particularsDays are calendar days from the date of awareness. Your Particular Conditions may change any of these periods, so check them first. This is a planning aid, not legal advice.
How to write a construction claim in the UAEHow to write a construction claim under FIDIC 20.1 on UAE and GCC projects: the 28-day notice, the 42-day detailed claim, sample wording and records.
8 min readRead the guide
How to claim an extension of time (EOT) under FIDICA guide to extension of time claims on UAE and GCC projects: grounds under FIDIC 8.4, the 28 and 42-day limits, delay analysis, prolongation costs and a sample.
8 min readRead the guide
How to give notice of a delayNotice of delay letter format for UAE and GCC projects: early warning (FIDIC 8.3), late drawings (1.9) and the 28-day notice of claim (20.1), with samples.
5 min readRead the guide