Employer and Main Contractor

Contractor prequalification questionnaire and scoring

EmployerMain Contractor
Clause
UAE practice
Time limit
Set by the agreement
Format
Word and ExcelLanguage: English
Stage
Pre-contract: 1. TenderRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Classification, turnover, completed projects, key staff, plant, safety record and litigation disclosure, scored by category.
  • Sent by the Employer to the Main Contractor.
  • Written to UAE practice.
  • Step 1 of 14 in the Main contract tender and award process.

What you get

Where it sits in the processes

Main contract tender and award, step 1 of 14View all
Start of the process
This documentContractor prequalification questionnaire and scoring
AfterPrequalification submission and company profile

Also used between