Employer and Main Contractor

Employer’s Requirements: structure and content checklist

EmployerMain Contractor
Clause
FIDIC 1999 Yellow BookSub-Clause 1.1.1.5
Time limit
Set by the agreement
Format
WordLanguage: English
Stage
Pre-contract: 1. TenderRoute: Design and Build

What this document does

  • Purpose, scope, performance criteria, standards, design submission procedure, authority approvals and the schedule of Employer’s Requirements, section by section.
  • Sent by the Employer to the Main Contractor.
  • Written to FIDIC 1999 Yellow Book, Sub-Clause 1.1.1.5.
  • For Design and Build projects only.

What you get