Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Main Contractor and Supplier

Factory and site acceptance test protocol

AED 129
Launch offerAED 64.50 on your first order, until 31 December.
SupplierMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 7.4
Time limit
Set by the agreement
Format
Word, 7 pagesExcel, 5 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 4. Build and monitorRoute: Both routes. Scope: Supply only, Supply and install, Design, supply and install, Services and supervision

What this document does

  • Test schedule, acceptance criteria, witness attendance and result sheets for equipment before shipping and after installation.
  • Sent by the Supplier to the Main Contractor.
  • Written to FIDIC 1999 Red Book, Sub-Clause 7.4.
  • Step 9 of 14 in the Specialist equipment procurement process.

What you get

Save with a pack

Supplier to Main Contractor: Build and monitor4 documents. Includes this document.
AED 256AED 169Save AED 87
Specialist equipment procurement process: Supplier steps7 documents. Includes this document.
AED 463AED 319Save AED 144

Free basic version or the full version

Free

Basic version

  • The English Word form, 7 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 129

  • The same Word form, with no line in the footer
  • Excel, 5 sheets
  • Your logo and company details on every file
How to write it

How to write a FAT and SAT protocol

A factory acceptance test (FAT) proves the equipment works before it leaves the factory; a site acceptance test (SAT) proves it still works after it is installed. Under Sub-Clause 7.4 of the FIDIC 1999 Red Book, the time and place of each test are agreed with the Engineer, who may attend.

What to include

  1. 1The equipment, its tags and serial numbers, and the order it belongs to
  2. 2The specification clauses, standards and approved documents the tests follow
  3. 3Each test with its acceptance criteria, and whether it is done at the factory or on site
  4. 4Who witnesses each test: vendor, contractor, Engineer and Employer
  5. 5The instruments used, with their calibration certificates
  6. 6The results, initialled at the time of the test
  7. 7The outcome: accepted, accepted with punch items, or retest needed, signed by all parties

When to use it

Submit the protocol for approval before the test date, then agree the time and place with the Engineer. The Engineer gives at least 24 hours’ notice of attending; if the Engineer does not attend as agreed, the test may go ahead and is treated as made in the Engineer’s presence.

Read the full guideMaterial submittals in construction: the package, approval codes and samples
Sample wording
We invite the Engineer to witness the factory acceptance test of the two standby generators, GEN-01 and GEN-02, at the manufacturer’s works on 14 and 15 July 2026, under Sub-Clause 7.4. The test follows protocol FAT-007 Rev 1, approved on 2 July 2026, and includes a four-hour load test at full rated load.

Common mistakes

  • Testing to a protocol that was never approved
  • Instruments with no valid calibration certificate
  • Shipping before the punch items from the factory test are closed or agreed
  • Sending the certified test reports to the Engineer late: they are due promptly

Questions people ask

Who pays for the Engineer to attend a factory test?

The contract decides. Many specifications make the contractor pay the travel of a set number of witnesses. Tests the Engineer adds that the contract does not require are a Variation under Sub-Clause 7.4, unless they show the item is defective.

Does passing the FAT mean the equipment is accepted?

No. The factory test shows the equipment works before shipping. It is accepted only after the site test and the Tests on Completion, and the Engineer may still reject anything found defective (Sub-Clause 7.5).

Where it sits in the processes

Specialist equipment procurement, step 9 of 14View all
BeforeExport and import licence checklist
This documentFactory and site acceptance test protocol
AfterShipping documents checklist