Factory and site acceptance test protocol
What this document does
- Test schedule, acceptance criteria, witness attendance and result sheets for equipment before shipping and after installation.
- Sent by the Supplier to the Main Contractor.
- Written to FIDIC 1999 Red Book, Sub-Clause 7.4.
- Step 9 of 14 in the Specialist equipment procurement process.
What you get
- Editable Word template
- Excel schedules and summary sheet
- Checklist of attachments
- A full Arabic copy of every file, right to left
- File: Word, 7 pages
- File: Excel, 5 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
Free basic version or the full version
Basic version
- The English Word form, 7 pages
- No payment and no sign-up
- A line in the footer: Free basic version from builderdraft.com
AED 129
- The same Word form, with no line in the footer
- Excel, 5 sheets
- Your logo and company details on every file
How to write a FAT and SAT protocol
A factory acceptance test (FAT) proves the equipment works before it leaves the factory; a site acceptance test (SAT) proves it still works after it is installed. Under Sub-Clause 7.4 of the FIDIC 1999 Red Book, the time and place of each test are agreed with the Engineer, who may attend.
What to include
- 1The equipment, its tags and serial numbers, and the order it belongs to
- 2The specification clauses, standards and approved documents the tests follow
- 3Each test with its acceptance criteria, and whether it is done at the factory or on site
- 4Who witnesses each test: vendor, contractor, Engineer and Employer
- 5The instruments used, with their calibration certificates
- 6The results, initialled at the time of the test
- 7The outcome: accepted, accepted with punch items, or retest needed, signed by all parties
When to use it
Submit the protocol for approval before the test date, then agree the time and place with the Engineer. The Engineer gives at least 24 hours’ notice of attending; if the Engineer does not attend as agreed, the test may go ahead and is treated as made in the Engineer’s presence.
We invite the Engineer to witness the factory acceptance test of the two standby generators, GEN-01 and GEN-02, at the manufacturer’s works on 14 and 15 July 2026, under Sub-Clause 7.4. The test follows protocol FAT-007 Rev 1, approved on 2 July 2026, and includes a four-hour load test at full rated load.
Common mistakes
- Testing to a protocol that was never approved
- Instruments with no valid calibration certificate
- Shipping before the punch items from the factory test are closed or agreed
- Sending the certified test reports to the Engineer late: they are due promptly
Questions people ask
Who pays for the Engineer to attend a factory test?
The contract decides. Many specifications make the contractor pay the travel of a set number of witnesses. Tests the Engineer adds that the contract does not require are a Variation under Sub-Clause 7.4, unless they show the item is defective.
Does passing the FAT mean the equipment is accepted?
No. The factory test shows the equipment works before shipping. It is accepted only after the site test and the Tests on Completion, and the Engineer may still reject anything found defective (Sub-Clause 7.5).