Final account statement and agreement
What this document does
- Original sum, variations, provisional sums, claims, deductions and retention reconciled to the balance due, with the sign-off page.
- Sent by the Main Contractor to the Employer.
- Written to FIDIC 1999 Red Book, Sub-Clause 14.11.
What you get
- Excel schedules and summary sheet
- Editable Word template
- One-page guide on when and how to use it
- Worked example
- A full Arabic copy of every file, right to left
- File: Excel, 8 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
How to prepare a final account
The final account reconciles the contract sum to the balance due: every variation, provisional sum, claim and deduction, valued and agreed. Under the FIDIC 1999 Red Book it feeds the draft final statement, due within 56 days after the Performance Certificate (Sub-Clause 14.11).
What to include
- 1The original contract sum
- 2The final measured quantities, where the contract is remeasured
- 3Every variation, with your value and the agreed value
- 4Provisional sums spent, with the sums in the contract omitted
- 5Claims and their status: agreed, determined or open
- 6Deductions, delay damages and contra charges
- 7Payments certified to date and the retention, giving the balance due
When to use it
Towards the end of the defects notification period, so the agreed figures can go into the draft final statement within 56 days after the Performance Certificate.
Contract sum AED 24,860,000. Variations agreed AED 1,412,300. Provisional sums adjusted, less AED 186,000. Claims agreed AED 540,000. Deductions AED 95,200. Final contract value AED 26,531,100. Less certified to date AED 25,710,000. Balance due AED 821,100 excluding VAT, with two open items listed on the agreement page.
Common mistakes
- Signing an agreement that leaves out open items without saying so
- Forgetting to omit unused provisional sums and contingencies
- Agreeing figures without the measurement and variation records behind them
Questions people ask
What is the difference between the final account and the Final Statement?
The final account is the agreed reconciliation of the value. The Final Statement under Sub-Clause 14.11 is the formal statement the Contractor submits, followed by the written discharge (14.12) and the Final Payment Certificate (14.13).
When is the retention fully released?
Half when the Taking-Over Certificate is issued, and the rest promptly after the latest expiry of the defects notification periods (Sub-Clause 14.9).