Free-issue materials issue and acceptance record
What this document does
- Records Employer-supplied materials handed to the contractor, their condition and the contractor’s acceptance.
- Sent by the Employer to the Main Contractor.
- Written to FIDIC 1999 Red Book, Sub-Clause 4.20.
What you get
- Excel register with automatic totals
- Fillable form
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
How to record free-issue materials
Free-issue materials are supplied by the Employer for the Contractor to install, such as equipment the Employer bought directly. Under Sub-Clause 4.20 of the FIDIC 1999 Red Book the Contractor inspects them visually when they are handed over and promptly notifies the Engineer of any shortage, defect or default. After that inspection they come under the Contractor’s care, custody and control.
What to include
- 1The list of free-issue items and quantities, from the contract
- 2Each delivery: the date, the quantity and who handed it over
- 3The visual inspection, its result and the quantity accepted
- 4Any shortage or defect, the date of the notice to the Engineer and the date it was put right
- 5The date custody passed to the Contractor
- 6The quantities installed and the balance still held by the Contractor
When to use it
At every handover of free-issue materials, before they go into storage. Notify a shortage or defect the same day, while the Employer can still put it right before it delays the work.
FI-012, item 4: lift car finishes kit for Lift 2. Delivered on 18 November 2026: 1 set of 1, in 6 crates. Visual inspection: crate 5 damaged, two stainless steel wall panels dented. Accepted except the two panels; notice sent to the Engineer under Sub-Clause 4.20 on the same day. Custody of the accepted items passed to the Contractor on 18 November 2026.
Common mistakes
- Signing for free-issue items without opening and inspecting them
- Reporting a shortage weeks later, when no one can show it was there on delivery
- Losing track of who holds the items, so loss or damage cannot be placed
Questions people ask
Is the Contractor responsible for hidden defects?
No. The visual inspection does not relieve the Employer of liability for a shortage, defect or default that a visual inspection could not reveal (Sub-Clause 4.20).
Who must put right a notified shortage or defect?
The Employer, immediately, unless both Parties agree otherwise (Sub-Clause 4.20). Record the date it was put right, in case the delay affects the programme.