Employer and Main Contractor

Free-issue materials issue and acceptance record

AED 59
Launch offerAED 29.50 on your first order, until 31 December.
EmployerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 4.20
Time limit
Set by the agreement
Format
Excel, 4 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 4. Build and monitorRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Records Employer-supplied materials handed to the contractor, their condition and the contractor’s acceptance.
  • Sent by the Employer to the Main Contractor.
  • Written to FIDIC 1999 Red Book, Sub-Clause 4.20.

What you get

How to write it

How to record free-issue materials

Free-issue materials are supplied by the Employer for the Contractor to install, such as equipment the Employer bought directly. Under Sub-Clause 4.20 of the FIDIC 1999 Red Book the Contractor inspects them visually when they are handed over and promptly notifies the Engineer of any shortage, defect or default. After that inspection they come under the Contractor’s care, custody and control.

What to include

  1. 1The list of free-issue items and quantities, from the contract
  2. 2Each delivery: the date, the quantity and who handed it over
  3. 3The visual inspection, its result and the quantity accepted
  4. 4Any shortage or defect, the date of the notice to the Engineer and the date it was put right
  5. 5The date custody passed to the Contractor
  6. 6The quantities installed and the balance still held by the Contractor

When to use it

At every handover of free-issue materials, before they go into storage. Notify a shortage or defect the same day, while the Employer can still put it right before it delays the work.

Sample wording
FI-012, item 4: lift car finishes kit for Lift 2. Delivered on 18 November 2026: 1 set of 1, in 6 crates. Visual inspection: crate 5 damaged, two stainless steel wall panels dented. Accepted except the two panels; notice sent to the Engineer under Sub-Clause 4.20 on the same day. Custody of the accepted items passed to the Contractor on 18 November 2026.

Common mistakes

  • Signing for free-issue items without opening and inspecting them
  • Reporting a shortage weeks later, when no one can show it was there on delivery
  • Losing track of who holds the items, so loss or damage cannot be placed

Questions people ask

Is the Contractor responsible for hidden defects?

No. The visual inspection does not relieve the Employer of liability for a shortage, defect or default that a visual inspection could not reveal (Sub-Clause 4.20).

Who must put right a notified shortage or defect?

The Employer, immediately, unless both Parties agree otherwise (Sub-Clause 4.20). Record the date it was put right, in case the delay affects the programme.