Employer and Design Consultant

Kick-off meeting agenda and minutes

EmployerDesign Consultant
Clause
UAE practice
Time limit
Set by the agreement
Format
Word, 5 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 3. Agreement and startRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Introduces the teams, confirms communication routes, submittal procedures and the first deliverables.
  • Sent by the Employer to the Design Consultant.
  • Written to UAE practice.

What you get

How to write it

How to run and record a kick-off meeting

The kick-off meeting starts an appointment or a contract on the right footing. It settles who decides what, how documents move and what is due first. Hold it within the first two weeks after the commencement date.

What to include

  1. 1Introductions, the representatives and what each may decide
  2. 2Communication routes, document numbering and transmittals
  3. 3Programme: the first deliverables and the date of the detailed programme
  4. 4Review periods for drawings, materials and method statements
  5. 5Site matters: access, logistics, health and safety
  6. 6The payment cycle: application dates and certification
  7. 7The meeting schedule and the date of the next meeting

When to use it

Within 14 days of the commencement date. Send the notice and agenda a week ahead, and issue the minutes within two working days.

Sample wording
Item 3, Communication. All letters will be addressed to the Engineer’s Representative and numbered from PRJ-ENG-L-0001. Drawings and submittals will be sent by transmittal through the document control system. Review periods: 14 days for drawings and 7 days for RFIs.

Common mistakes

  • No decision on who may give instructions
  • Leaving review periods and document numbering to be agreed later
  • Minutes that try to change contract terms: a meeting cannot amend the contract

Questions people ask

Who chairs the kick-off meeting?

The issuing party: the Employer or its Engineer for the main contract, the main contractor for a subcontract, and the client for a consultancy appointment.

Can the kick-off meeting change the contract?

No. The minutes record how the parties will work together. A change to the terms needs a formal variation or amendment, signed as the contract requires.

Also used between