Engineer and Main Contractor

Progress meeting minutes and action tracker

EngineerMain Contractor
Clause
UAE practice
Time limit
Set by the agreement
Format
Word, 5 pagesExcel, 3 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 4. Build and monitorRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Decisions, owners and dates, with actions tracked until they close.
  • Sent by the Engineer to the Main Contractor.
  • Written to UAE practice.

What you get

How to write it

How to write construction meeting minutes

Good minutes record decisions and actions, not conversations. Each action has one owner and one date, and open actions are carried forward until they close. Minutes do not change the contract, but minutes left unchallenged become strong evidence later.

What to include

  1. 1The meeting number, date, place and attendees with their organisations
  2. 2Review of the previous minutes and the open actions
  3. 3Progress against the programme, by area or trade
  4. 4Design, submittals, RFIs and inspections outstanding
  5. 5Health, safety and quality items
  6. 6Decisions, and new actions with one owner and one date each
  7. 7The date of the next meeting and the distribution list

When to use it

Issue the minutes within two working days of the meeting, and ask for comments within a set period, such as three working days. Correct wrong minutes in writing at once.

Sample wording
Item 4.2, Facade. The Contractor reported that the curtain wall mock-up will be ready on 15 September 2026. Action: the Contractor to submit the mock-up test procedure by 5 September 2026. Owner: the Contractor’s facade manager.

Common mistakes

  • Actions with no owner or no date
  • Minutes written days later from memory
  • Treating minutes as an instruction or a notice, instead of confirming instructions in writing and sending notices separately

Questions people ask

Is an instruction given at a meeting valid?

Under Sub-Clause 3.3 of the FIDIC 1999 Red Book instructions are given in writing. An oral instruction that the Contractor confirms in writing within two working days becomes a written instruction unless the Engineer rejects it or instructs otherwise within two working days.

Who writes the minutes?

Usually the party that chairs the meeting: the Engineer for progress meetings under the main contract, and the main contractor for its subcontractor meetings.

Also used between