Progress meeting minutes and action tracker
What this document does
- Decisions, owners and dates, with actions tracked until they close.
- Sent by the Engineer to the Main Contractor.
- Written to UAE practice.
What you get
- Editable Word template
- Excel register with automatic totals
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Word, 5 pages
- File: Excel, 3 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
How to write construction meeting minutes
Good minutes record decisions and actions, not conversations. Each action has one owner and one date, and open actions are carried forward until they close. Minutes do not change the contract, but minutes left unchallenged become strong evidence later.
What to include
- 1The meeting number, date, place and attendees with their organisations
- 2Review of the previous minutes and the open actions
- 3Progress against the programme, by area or trade
- 4Design, submittals, RFIs and inspections outstanding
- 5Health, safety and quality items
- 6Decisions, and new actions with one owner and one date each
- 7The date of the next meeting and the distribution list
When to use it
Issue the minutes within two working days of the meeting, and ask for comments within a set period, such as three working days. Correct wrong minutes in writing at once.
Item 4.2, Facade. The Contractor reported that the curtain wall mock-up will be ready on 15 September 2026. Action: the Contractor to submit the mock-up test procedure by 5 September 2026. Owner: the Contractor’s facade manager.
Common mistakes
- Actions with no owner or no date
- Minutes written days later from memory
- Treating minutes as an instruction or a notice, instead of confirming instructions in writing and sending notices separately
Questions people ask
Is an instruction given at a meeting valid?
Under Sub-Clause 3.3 of the FIDIC 1999 Red Book instructions are given in writing. An oral instruction that the Contractor confirms in writing within two working days becomes a written instruction unless the Engineer rejects it or instructs otherwise within two working days.
Who writes the minutes?
Usually the party that chairs the meeting: the Engineer for progress meetings under the main contract, and the main contractor for its subcontractor meetings.