Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

Advance payment application

AED 59
Launch offerAED 29.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 14.2
Time limit
Set by the agreement
Format
Word, 3 pagesExcel, 8 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 6. PaymentsRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Applies for the advance against the guarantee delivered, with the recovery schedule.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 14.2.

What you get

Save with a pack

Main Contractor to Engineer: Payments6 documents. Includes this document.
AED 594AED 389Save AED 205

Free basic version or the full version

Free

Basic version

  • The English Word form, 3 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 59

  • The same Word form, with no line in the footer
  • Excel, 8 sheets
  • Cover letter
  • One-page guide on when and how to use it
  • Your logo and company details on every file
How to write it

How to apply for the advance payment

The advance payment is an interest-free loan for mobilisation. Under Sub-Clause 14.2 of the FIDIC 1999 Red Book, the Engineer certifies it after the Employer receives the Performance Security and an advance payment guarantee for the same amount, and the Contractor sends a Statement. It is repaid by deductions from later payment certificates.

What to include

  1. 1The contract, the advance amount and the instalment applied for, as in the Appendix to Tender
  2. 2Confirmation that the Performance Security has been delivered (Sub-Clause 4.2)
  3. 3The advance payment guarantee: bank, number, amount and expiry date
  4. 4The Statement and the tax invoice for the instalment
  5. 5The repayment schedule: when deductions start and the rate of each deduction
  6. 6The bank details for payment

When to use it

Once the Performance Security and the advance payment guarantee have been delivered. The Employer pays the first instalment within 42 days after the Letter of Acceptance, or within 21 days after receiving both securities, whichever is later (Sub-Clause 14.7).

Read the full guideClear to pay: the checklist before the first payment
Sample wording
Under Sub-Clause 14.2 we apply for the advance payment of AED 4,500,000, being 10% of the Accepted Contract Amount. The Performance Security was delivered on 3 March 2026, and advance payment guarantee No. G-2291 from our bank, for AED 4,500,000 and valid until 31 December 2027, is enclosed with our Statement and tax invoice.

Common mistakes

  • Applying before both guarantees have reached the Employer
  • A guarantee that expires before the advance is repaid: extend it 28 days before expiry
  • Forgetting the tax invoice, so the payment cannot be processed

Questions people ask

How is the advance repaid?

Unless the Appendix to Tender says otherwise, deductions start when certified interim payments pass 10% of the Accepted Contract Amount less Provisional Sums, at 25% of each certificate, until the advance is repaid. Any balance is due at taking over.

Can the guarantee be reduced as the advance is repaid?

Yes. Sub-Clause 14.2 lets the amount of the guarantee be reduced progressively by the amounts repaid, as shown in the payment certificates. Ask the bank to reduce it at each step.