Design review comment sheet (A, B, C status)
What this document does
- Numbered comments with the status code: approved, approved with comments, revise and resubmit.
- Sent by the Employer to the Design Consultant.
- Written to UAE practice.
- Time limit: Review period fixed in the agreement, commonly 14 to 21 days.
- Goes with: Design review response sheet
- Step 7 of 15 in the Design appointment and design development process.
What you get
- Excel register with automatic totals
- One-page guide on when and how to use it
- Worked example
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to review a design submission
Every design submission, from concept to tender documents, should be reviewed the same way. Reviewers write numbered comments against each drawing or document and give each document a status code, and the consultant answers every comment. The sheet shows what is still open and whether the review went back on time.
What to include
- 1The submission, its reference and revision, the date received and the date due
- 2The list of documents reviewed, each with its status code
- 3Numbered comments, each against one document and one discipline
- 4The status codes: A approved, B approved with comments, C revise and resubmit
- 5The consultant’s response to each comment
- 6Whether each comment is open or closed, and who closed it
When to use it
Within the review period in the consultancy agreement, commonly 14 to 21 days from receipt. Send the sheet back with the overall status, then close each comment as the consultant’s next revision resolves it.
Comment 23, drawing A-301 Rev B, architecture: the corridor at gridline 7 is shown 1,100 mm wide; the brief requires 1,500 mm in the clinic wing. Please revise. Document status: C, revise and resubmit.
Common mistakes
- Returning comments after the review period, which can delay the design and give the consultant a claim for time
- Vague comments that cannot be acted on
- Using comments to change the brief instead of a change request
Questions people ask
How is the overall status worked out?
One document coded C makes the whole submission C. With no C and at least one B, the submission is B. A submission is A only when every document is coded A.
Does approval make the client responsible for the design?
No. Reviewing and approving a design does not take over the consultant’s responsibility for it, which stays with the consultant under the agreement.