Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

Interim payment application with statement and schedules

AED 149
Launch offerAED 74.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 14.3
Time limit
Monthly, after the end of each period
Format
Excel, 7 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 6. PaymentsRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Statement under items (a) to (g) of Sub-Clause 14.3 with measured works, variations, materials on site, retention, advance repayment and the certificate log, in the layout certifiers expect.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 14.3.
  • Time limit: Monthly, after the end of each period.
  • Goes with: Interim payment certificate
  • Step 4 of 9 in the Payment process.

What you get

  • Excel schedules and summary sheet
  • Worked example
  • Cover letter
  • Checklist of attachments
  • One-page guide on when and how to use it
  • A full Arabic copy of every file, right to left
  • File: Excel, 7 sheets
  • Language: English, plus a full Arabic copy
  • Brand-ready: your logo and company details go in when you download
  • Pay once and use it on every project

Save with a pack

Main Contractor to Engineer: Payments6 documents. Includes this document.
AED 594AED 389Save AED 205
Payment process: Main Contractor steps5 documents. Includes this document.
AED 535AED 369Save AED 166
How to write it

How to prepare an interim payment application

Each month the Contractor sends the Engineer a Statement of the amounts it considers due, with the supporting documents and the progress report. Under the FIDIC 1999 Red Book the Engineer certifies within 28 days of receiving it, and the Employer pays within 56 days. Both clocks start when the Statement arrives.

What to include

  1. 1(a) The value of the work executed to the end of the month, including Variations
  2. 2(b) Adjustments for changes in legislation and in cost, where the contract allows them
  3. 3(c) The retention deduction, at the rate and up to the limit in the Appendix to Tender
  4. 4(d) The advance payment and its repayments
  5. 5(e) Plant and Materials on Site, with the evidence Sub-Clause 14.5 requires
  6. 6(f) Other additions or deductions due under the contract, including agreed claims
  7. 7(g) Less the amounts certified in all previous Payment Certificates

When to use it

Monthly, after the end of each period, in the form the Engineer approves (Sub-Clause 14.3). The Engineer issues the Interim Payment Certificate within 28 days after receiving the Statement and supporting documents (14.6), and the Employer pays within 56 days after the Engineer receives them (14.7).

Read the full guideHow interim payment applications work under FIDIC
Sample wording
We submit Interim Payment Application No. 6 for the period ending 31 May 2026 under Sub-Clause 14.3. The value of the work executed to date is AED 18,450,000. After retention, advance repayment and the amounts previously certified, the net amount due is AED 1,327,500 excluding VAT. The measurement records, the evidence for materials on site and the monthly progress report are attached.

Common mistakes

  • Including Variations the Engineer has not instructed
  • Claiming materials on site without invoices, delivery notes and storage evidence
  • Deducting the amounts applied for previously instead of the amounts certified
  • Sending late or without the supporting documents: the 28 days start only when both arrive

Questions people ask

Can the Engineer certify less than I applied for?

Yes, in limited cases. Under Sub-Clause 14.6 the Engineer may withhold the cost of putting right work that does not comply, or the value of work you were notified you are failing to do, and may correct earlier certificates. A certificate cannot be withheld for any other reason, apart from the minimum amount in the Appendix to Tender.

Is VAT included?

Amounts are usually applied for and certified before VAT, and the tax invoice adds VAT at the rate of your country, 5% in the UAE, with your tax registration number.

Where it sits in the processes

Payment, step 4 of 9View all
BeforeSubcontract payment assessment and certificate
This documentInterim payment application with statement and schedules
AfterInterim payment certificate