Letter of intent
What this document does
- For the exceptional case where work must start before the agreement is signed, with a cap and an expiry.
- Sent by the Employer to the Design Consultant.
- Written to UAE practice.
- Step 12 of 14 in the Subcontract tender and award process.
What you get
- Editable Word template
- An English copy, and a copy with English and Arabic side by side
- One-page guide on when and how to use it
- File: Word, 4 pages
- File: English and Arabic copy, 4 pages
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write a letter of intent
A letter of intent lets limited work start before the contract is signed. It is an exception, used only when the programme cannot wait. A good letter limits what may be done, caps the cost, sets an expiry date and says which terms apply.
What to include
- 1The authorised activities, listed precisely
- 2A cap on the amount payable for them
- 3An expiry date, usually four to eight weeks ahead
- 4The terms that apply: the draft contract or the clarified tender
- 5How the letter ends, and what is paid if no contract follows
- 6That the letter is not the whole contract
- 7An acceptance block for the recipient to sign and return
When to use it
Only when work must start before the contract or agreement is signed. The normal route is the letter of award followed by the signed contract.
Pending the signature of the subcontract agreement, you are authorised to prepare shop drawings and to order the long-lead switchgear for the project, up to a maximum of AED 350,000 excluding VAT. This authority expires on 30 November 2026. If no subcontract is signed, we will pay the reasonable cost of the authorised work, up to that maximum, against evidence.
Common mistakes
- No cap, so costs run without control
- No expiry date, so the letter runs for months and the terms are disputed
- A scope wider than the contract you intend to sign
Questions people ask
Is a letter of intent binding?
It can be, depending on its wording and on what the parties do under it. That is why the letter should state the authorised work, the cap, the terms and the expiry date clearly.
What if the contract is never signed?
A well-drafted letter says what is paid for the authorised work up to the cap, and that nothing else is due.