Employer and Main Contractor

Acknowledgement of award and pre-contract checklist

Main ContractorEmployer
Clause
FIDIC 1999 Red Book
Time limit
Set by the agreement
Format
WordLanguage: English
Stage
Pre-contract: 2. Evaluation and awardRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Accepts the award and lists what is due before and after signing: performance security, insurances, advance payment guarantee and the programme, each with its deadline.
  • Sent by the Main Contractor to the Employer.
  • Written to FIDIC 1999 Red Book.
  • Step 14 of 14 in the Main contract tender and award process.
  • Step 13 of 14 in the Subcontract tender and award process.

What you get

Where it sits in the processes

Main contract tender and award, step 14 of 14View all
BeforeLetter of award
This documentAcknowledgement of award and pre-contract checklist
End of the process
Subcontract tender and award, step 13 of 14View all
BeforeLetter of intent
This documentAcknowledgement of award and pre-contract checklist
AfterSubcontract agreement, supply and installation

Also used between