Method statement submittal
What this document does
- Sequence, resources, access, quality checks and safety controls for an activity, in the form reviewers expect.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 8.3.
What you get
- Editable Word template
- Checklist of attachments
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Word, 12 pages
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write a method statement
A method statement shows how an activity will be carried out safely and to the specified quality. The Engineer reviews it before the work starts, and the site team follows it. Under the FIDIC 1999 Red Book the Contractor remains responsible for the adequacy and safety of all methods of construction (Sub-Clause 4.1).
What to include
- 1The scope of the activity and where it takes place
- 2References: drawings, specification sections and approved materials
- 3Resources: competent people, certified plant and the materials used
- 4The sequence of work in numbered steps, with hold points for inspection
- 5Access, temporary works and control of the work area
- 6Quality checks, linked to the inspection and test plan
- 7Hazards and their controls, with the risk assessment attached
When to use it
Before each significant activity starts, allowing the review period, and whenever the Engineer asks. Submit a revision before any significant change to the method.
Scope: casting the Level 3 slab, 850 cubic metres, with a boom pump. Step 4: pour in two bays starting from grid 1, checking slump and temperature on every truck and taking cubes every 50 cubic metres. Hold point: the Engineer’s inspection of reinforcement and embedded services before the pour (IR-215).
Common mistakes
- A statement copied from another project, the most common reason for rejection
- Steps that do not match the programme or the drawings
- No hold points before work is covered up
- Hazards listed without controls or the person responsible
Questions people ask
What is the difference between a method statement and a RAMS?
A method statement describes how the work is done. A RAMS adds the risk assessment, and many sites in the UAE ask for it before a permit to work is issued.
Does the Engineer’s review make the method the Engineer’s responsibility?
No. The Contractor stays responsible for the adequacy and safety of its methods (Sub-Clause 4.1), even after the review.