Engineer and Main Contractor

Method statement submittal

AED 79
Launch offerAED 39.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 8.3
Time limit
Set by the agreement
Format
Word, 12 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 4. Build and monitorRoute: Both routes. Scope: Supply and install, Install only, Design, supply and install, Labour only
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Sequence, resources, access, quality checks and safety controls for an activity, in the form reviewers expect.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 8.3.

What you get

Save with a pack

Main Contractor to Engineer: Build and monitor16 documents. Includes this document.
AED 1,126AED 729Save AED 397
How to write it

How to write a method statement

A method statement shows how an activity will be carried out safely and to the specified quality. The Engineer reviews it before the work starts, and the site team follows it. Under the FIDIC 1999 Red Book the Contractor remains responsible for the adequacy and safety of all methods of construction (Sub-Clause 4.1).

What to include

  1. 1The scope of the activity and where it takes place
  2. 2References: drawings, specification sections and approved materials
  3. 3Resources: competent people, certified plant and the materials used
  4. 4The sequence of work in numbered steps, with hold points for inspection
  5. 5Access, temporary works and control of the work area
  6. 6Quality checks, linked to the inspection and test plan
  7. 7Hazards and their controls, with the risk assessment attached

When to use it

Before each significant activity starts, allowing the review period, and whenever the Engineer asks. Submit a revision before any significant change to the method.

Sample wording
Scope: casting the Level 3 slab, 850 cubic metres, with a boom pump. Step 4: pour in two bays starting from grid 1, checking slump and temperature on every truck and taking cubes every 50 cubic metres. Hold point: the Engineer’s inspection of reinforcement and embedded services before the pour (IR-215).

Common mistakes

  • A statement copied from another project, the most common reason for rejection
  • Steps that do not match the programme or the drawings
  • No hold points before work is covered up
  • Hazards listed without controls or the person responsible

Questions people ask

What is the difference between a method statement and a RAMS?

A method statement describes how the work is done. A RAMS adds the risk assessment, and many sites in the UAE ask for it before a permit to work is issued.

Does the Engineer’s review make the method the Engineer’s responsibility?

No. The Contractor stays responsible for the adequacy and safety of its methods (Sub-Clause 4.1), even after the review.