Fit-out approvals and handover

The landlord’s NOC and design approval, the fit-out permit, works in an occupied building, samples and mock-ups, Civil Defence completion and the handover to the landlord and the tenant.

Show steps for
12 steps in this process
LandlordEmployerDesign ConsultantFit-out ContractorFit-out contract agreement, lump sumFit-out contractagreement, lump sum1Landlord fit-out NOC applicationLandlord fit-out NOCapplication2Landlord design submission and comments logLandlord designsubmission andcomments log3Fit-out permit and authority approvals trackerFit-out permit andauthority approvalstracker4Site rules and protection plan for an occupied buildingSite rules andprotection plan foran occupied building5Building management permit and access request setBuilding managementpermit and accessrequest set6Finishes and samples board approvalFinishes and samplesboard approval7Mock-up approval recordMock-up approvalrecord8Inspection request and logInspection requestand log9Civil Defence inspection and completion certificate checklistCivil Defenceinspection and…10Landlord final inspection and fit-out deposit refund requestLandlord finalinspection andfit-out…11Fit-out completion and handover packFit-out completionand handover pack12
1Fit-out contract agreement, lump sum
EmployerFit-out Contractor
AED 249
2Landlord fit-out NOC application
Fit-out ContractorLandlord
Before any work starts on site
AED 99
3Landlord design submission and comments log
Fit-out ContractorLandlord
AED 99
4Fit-out permit and authority approvals tracker
Fit-out Contractor, internal step
AED 99
5Site rules and protection plan for an occupied building
Fit-out ContractorLandlord
AED 79
6Building management permit and access request set
Fit-out ContractorLandlord
Usually 24 to 48 hours ahead
AED 79
7Finishes and samples board approval
Fit-out ContractorInterior Designer
AED 79
8Mock-up approval record
Fit-out ContractorInterior Designer
AED 59
9Inspection request and log
Fit-out ContractorInterior Designer
Notice before covering up work, commonly 24 hours
AED 79
10Civil Defence inspection and completion certificate checklist
Fit-out ContractorInterior Designer
AED 79
12Fit-out completion and handover pack
Fit-out ContractorEmployer
AED 149