Inspection request and log

AED 79
Launch offerAED 39.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 7.3
Time limit
Notice before covering up work, commonly 24 hours
Format
Excel, 4 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 4. Build and monitorRoute: Both routes. Scope: Supply and install, Install only, Design, supply and install, Labour only
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Books an inspection of work before it is covered and records pass, fail and re-inspection.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 7.3.
  • Time limit: Notice before covering up work, commonly 24 hours.
  • Step 1 of 6 in the Inspection and quality process.
  • Step 12 of 17 in the Fit-out approvals and handover process.

What you get

Save with a pack

Main Contractor to Engineer: Build and monitor16 documents. Includes this document.
AED 1,126AED 729Save AED 397
Inspection and quality process: Main Contractor steps3 documents. Includes this document.
AED 207AED 139Save AED 68
How to write it

How to write an inspection request

An inspection request, often called an IR or WIR, gives the Engineer notice that work is ready for inspection before it is covered up or put out of sight. Under Sub-Clause 7.3 of the FIDIC 1999 Red Book the Engineer then inspects without unreasonable delay, or says that no inspection is needed.

What to include

  1. 1The request number, the discipline and the activity
  2. 2The exact location: building, level, grids and area
  3. 3The drawings and the inspection and test plan item
  4. 4The date and time the work will be ready
  5. 5Your own check, done first, with the checklist attached
  6. 6Space for the result: approved, approved with comments or rejected, with signatures

When to use it

Before work is covered up, with the notice the project sets, commonly 24 hours. If work is covered without notice, the Engineer may have it uncovered and made good at your cost (Sub-Clause 7.3).

Read the full guideSite inspections in construction: the ITP, inspection requests and NCRs
Sample wording
IR-215, Civil. Reinforcement and embedded services for the Level 3 slab, grids 1 to 6 and A to F, to drawings S-301 Rev C and M-305 Rev B. Ready for inspection on 14 July 2026 at 08:00. Our own check is complete and the checklist is attached.

Common mistakes

  • Asking for an inspection before checking the work yourself
  • Covering work before the inspection or without notice
  • Not recording rejections and re-inspections, which hides the real first-time pass rate

Questions people ask

How much notice should I give?

The notice set in the specification or the communication protocol, commonly 24 hours. Keep the request with the time it was sent: it is your evidence that notice was given.

What happens after a rejection?

Correct the work, check it again and raise a new request that refers to the rejected one, so the log shows every re-inspection.

Where it sits in the processes

Inspection and quality, step 1 of 6View all