Inspection request and log
What this document does
- Books an inspection of work before it is covered and records pass, fail and re-inspection.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 7.3.
- Time limit: Notice before covering up work, commonly 24 hours.
- Step 1 of 6 in the Inspection and quality process.
- Step 12 of 17 in the Fit-out approvals and handover process.
What you get
- Fillable form
- Log with status and ageing
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write an inspection request
An inspection request, often called an IR or WIR, gives the Engineer notice that work is ready for inspection before it is covered up or put out of sight. Under Sub-Clause 7.3 of the FIDIC 1999 Red Book the Engineer then inspects without unreasonable delay, or says that no inspection is needed.
What to include
- 1The request number, the discipline and the activity
- 2The exact location: building, level, grids and area
- 3The drawings and the inspection and test plan item
- 4The date and time the work will be ready
- 5Your own check, done first, with the checklist attached
- 6Space for the result: approved, approved with comments or rejected, with signatures
When to use it
Before work is covered up, with the notice the project sets, commonly 24 hours. If work is covered without notice, the Engineer may have it uncovered and made good at your cost (Sub-Clause 7.3).
IR-215, Civil. Reinforcement and embedded services for the Level 3 slab, grids 1 to 6 and A to F, to drawings S-301 Rev C and M-305 Rev B. Ready for inspection on 14 July 2026 at 08:00. Our own check is complete and the checklist is attached.
Common mistakes
- Asking for an inspection before checking the work yourself
- Covering work before the inspection or without notice
- Not recording rejections and re-inspections, which hides the real first-time pass rate
Questions people ask
How much notice should I give?
The notice set in the specification or the communication protocol, commonly 24 hours. Keep the request with the time it was sent: it is your evidence that notice was given.
What happens after a rejection?
Correct the work, check it again and raise a new request that refers to the rejected one, so the log shows every re-inspection.