Daily site report
What this document does
- Labour, plant, weather, work done and events each day, the record every delay claim is built on.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 6.10.
What you get
- Excel register with automatic totals
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
How to write a daily site report
The daily site report records what happened on site each day: people, plant, weather, work done and anything that stopped the work. Claims under Sub-Clause 20.1 of the FIDIC 1999 Red Book rest on contemporary records, and the daily report is the first of them.
What to include
- 1The date, the weather and the working hours
- 2The workforce by trade and by subcontractor
- 3Plant and equipment on site, working and idle
- 4Work done by area, linked to the programme activities
- 5Delays and stoppages, with times and causes
- 6Instructions received, visitors, inspections and safety events
- 7Signatures of the site engineer and the Engineer’s representative
When to use it
Every working day, filled in before leaving the site and signed by the Engineer’s representative. Sub-Clause 6.10 also asks for monthly records of personnel and equipment.
16 June 2026. Weather: 43 degrees, work stopped from 12:30 to 15:00 for the midday break. Workforce: 186. Plant: two tower cranes and one concrete pump. Work done: Level 4 slab reinforcement, grids 1 to 4, completed. Delay: late concrete delivery, pour moved from 07:00 to 10:15.
Common mistakes
- Filling in the report days later, when it carries far less weight
- Writing “work in progress” instead of the activity and its location
- Not noting who gave an instruction and when
Questions people ask
Why should the Engineer’s representative sign it?
A report signed by both sides is hard to dispute later. If it is not signed, keep sending it and record the date it was sent.
How long should daily reports be kept?
At least until the final account is agreed and every claim is closed. Many companies keep project records for years after that.