How to give notice of a delay

Delays are won or lost on notices. Under the FIDIC 1999 Red Book three notices matter: an early warning of likely problems, a notice when drawings or instructions are needed, and the notice of claim within 28 days.

5 min read FIDIC 1999 Red Book UAE and GCC

Early warning: Sub-Clause 8.3

The Contractor must promptly give notice of specific probable future events or circumstances that may adversely affect the work, increase the Contract Price or delay the execution of the Works. The Engineer may then ask for an estimate of the effect and a proposal under Sub-Clause 13.3.

Late drawings or instructions: Sub-Clause 1.9

When the work is likely to be delayed or disrupted if a drawing or instruction is not issued in time, give the Engineer notice of what is needed, why, by when, and the delay or disruption likely if it is late. If the delay or cost then happens, give a further notice: subject to Sub-Clause 20.1 you are entitled to an extension of time and the Cost plus reasonable profit, unless the lateness was caused by your own error or delay.

Notice of claim: Sub-Clause 20.1

Whatever the cause, give a notice of claim within 28 days after you became aware, or should have become aware, of the event. This notice protects your right to time and money; the earlier notices do not replace it.

PromptlyEarly warning of a likely problem (Sub-Clause 8.3)
In timeNotice of a drawing or instruction needed (Sub-Clause 1.9)
28 daysNotice of claim (Sub-Clause 20.1)
21 daysA subcontractor’s notice to the main contractor under the FIDIC Subcontract 2011 approach

What a delay notice should say

  • The event and its date, and the date you became aware of it
  • The activities affected and the likely delay
  • The cause and the Sub-Clauses relied on
  • What you are doing to reduce the delay
  • What you need from the Engineer, and by when
  • A reservation of your rights under Sub-Clause 20.1
Sample wording
We give notice under Sub-Clauses 8.3 and 20.1 that the approval of the facade shop drawings, submitted on 2 June 2026 and due by 16 June 2026, has not been given. The facade installation, on the critical path, is likely to be delayed by about 3 weeks from 7 July 2026. We have moved the facade crew to the podium works to reduce the effect. We ask for your approval by 25 June 2026 and reserve our rights to an extension of time and Cost.

Subcontractors: shorter periods

A subcontractor’s notice period must be shorter than the main contract’s, so the main contractor can pass the notice on in time. Under the FIDIC Subcontract 2011 approach the subcontractor gives notice within 21 days.

Keep the records from day one

Daily site reports, programme updates and dated photographs are what prove a delay later. Start them on the day the event happens.

Templates for each step

Early warning notice
Word
AED 39
AED 79
Notice of claim
Word
AED 59
AED 59
Daily site report
Excel
AED 49
AED 99

More guides

All guides