Non-conformance report and log
What this document does
- Records the defect, the corrective and preventive action and the close-out, with a log for audit.
- Sent by the Engineer to the Main Contractor.
- Written to FIDIC 1999 Red Book, Sub-Clause 7.5.
- Step 3 of 6 in the Inspection and quality process.
What you get
- Fillable form
- Log with status and ageing
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write a non-conformance report (NCR)
An NCR records work, Plant or Materials that do not comply with the contract, the action to correct them and the close-out. Under Sub-Clause 7.5 of the FIDIC 1999 Red Book the Engineer may reject them with reasons, and the Contractor then makes good the defect.
What to include
- 1The NCR number, date, location and discipline
- 2What does not comply, with photographs
- 3The requirement it breaks: drawing, specification clause or standard
- 4Whether the work must stop, and how serious it is
- 5The Contractor’s correction, the root cause and the preventive action
- 6Re-inspection and close-out, with signatures and the date
When to use it
As soon as the non-compliance is found, at an inspection, a test or a review. Close it only after the corrected work has been inspected again.
NCR-031, Finishes. Gypsum ceiling boards on Level 6, rooms 601 to 608, are fixed at 600 mm centres instead of the 400 mm required by specification Section 09 21 16, clause 3.4. Work to stop in the affected rooms. The Contractor is to remove and refix the boards and propose a preventive action by 22 August 2026.
Common mistakes
- Describing the defect without the requirement it breaks
- Closing an NCR on a promise instead of a re-inspection
- No root cause, so the same defect comes back
Questions people ask
Who issues an NCR?
Usually the Engineer or the Contractor’s own quality team, and a main contractor also raises them on its subcontractors. The steps are the same: record, correct, inspect again and close.
Who pays for retesting?
Under Sub-Clause 7.5, where the rejection and retesting cause the Employer additional costs, the Contractor pays them, subject to Sub-Clause 2.5.