Guide

Site inspections in construction: the ITP, inspection requests and NCRs

Most rework on site starts with an inspection that was skipped, rushed or never recorded: steel covered before anyone looked at it, a ceiling closed over untested pipes, a failed cube result nobody could trace. This guide follows the work from the inspection and test plan to the signed record, with the time limits, what to check at each stage and sample wording.

8 min read FIDIC 1999 Clauses 4.9 and 7 UAE and GCC
A site engineer checking reinforcement and spacers on a slab before a concrete pour, with the supervision engineer

The time limits

Before the work startsThe inspection and test plan for the activity submitted and accepted, with its hold and witness points (FIDIC 4.9 and the Specification)
Commonly 24 hoursNotice of an inspection request before work is covered, as the Specification or the communication protocol sets (7.3)
Without unreasonable delayThe Engineer inspects the work, or tells the Contractor that no inspection is needed (7.3)
24 hoursThe Engineer’s notice of intention to attend a test. If the Engineer does not attend, the test may go ahead and counts as witnessed (7.4)
7 and 28 daysThe usual ages for testing concrete cubes, with the 28-day result deciding acceptance of the strength
Set in the NCRThe date for corrective work and re-inspection. If the Contractor does not act, the Employer may have the work done by others at the Contractor’s cost (7.6)

The FIDIC 1999 Red Book sets the framework: the Contractor runs a quality assurance system (Sub-Clause 4.9), gives the Engineer the chance to inspect work before it is covered (7.3), carries out the tests the contract specifies (7.4), and puts right work the Engineer rejects (7.5 and 7.6). The detail, such as notice periods, tolerances and test frequencies, sits in the Specification, so check it first.

From the plan to the signed record

  1. 1
    Inspection and test plan

    For each activity, list what is checked, against which standard, how often, the record kept and who inspects at each point. Submit it with the method statement before the work starts.

  2. 2
    Your own check first

    The Contractor’s engineer checks the work against the checklist and puts right what is wrong before anyone else is called.

  3. 3
    Inspection request

    Give the Engineer notice that the work is ready, with the location, the drawings, the plan item and the completed checklist.

  4. 4
    Joint inspection

    The Engineer inspects, or says that no inspection is needed. Comments are written on the request, not given by word of mouth.

  5. 5
    Result

    Approved: the work goes on. Approved with comments: close the comments first. Rejected: put it right and raise a new request, or a non-conformance report where the work does not meet the Specification.

  6. 6
    Close the record

    File the signed request, the checklist, the test results and the photographs against the plan item, so the record proves every hold point was released.

Hold, witness and review points

An inspection and test plan marks each check with the level of involvement the Engineer wants. The letters vary between projects, so define them in the plan itself.

PointWhat it meansTypical examples
H, hold pointWork stops until the Engineer has inspected and released itReinforcement before a pour, pipework before it is buried or closed in, waterproofing before its protection
W, witness pointThe Engineer is told in advance and may attend; work goes on if the Engineer does not comePressure tests, pile load tests, concrete cube sampling
R, review pointThe Engineer reviews the records, not the work itselfMill certificates, delivery notes, calibration certificates
S, surveillanceThe Engineer may check at any time without noticeBlockwork in progress, curing, housekeeping

Keep hold points for checks that cannot be made later. A plan where everything is a hold point slows the site and teaches people to ignore it.

Reinforcement and formwork before a pour

This is the inspection most often rushed, because the concrete is already ordered. Check the formwork and the steel together, and make sure the MEP trades have signed off what is cast in before you call the Engineer.

  • Formwork: line, level and dimensions within the Specification tolerances, props and bracing as the formwork design, tight joints, and clean, oiled faces
  • Reinforcement: bar sizes, numbers and spacing as the bar schedule, cover with the right spacers, laps and anchorage, starter bars and couplers
  • Steel clean of loose rust, oil and mud, with its mill certificates checked and heat numbers traced
  • Embedded items: sleeves, conduits, boxes, cast-in plates and water stops in place and signed off
  • Ready to pour: area clean and dry, pump position and access agreed, and the concrete order confirmed only after the inspection is passed
Sample wording
IR-342, Civil. Reinforcement, formwork and embedded services for the Level 4 slab, grids 7 to 12 and C to H, to drawings S-404 Rev B and M-410 Rev A and bar schedule BS-404 Rev A. ITP item 3.4, hold point. Our own check is complete, and checklist RC-118, signed by the MEP trades, is attached. Ready for inspection on 18 November 2026 at 07:30, with the pour planned for 13:00 subject to your release.

Concrete and steel records

The inspection releases the pour, but the record goes on. A pour card ties each element to its concrete and its test results.

  • Pour card: the element, the delivery tickets, the grade, the slump or flow on site, the time from batching to placing, and the concrete temperature in hot weather
  • Cube register: the cube set reference, the element, and the 7 and 28-day results against the specified strength
  • Mill certificates: heat numbers traced from the bar tag to the certificate and to the element where the steel was installed

Write the element and its grid reference on every cube set and every heat number record. When a result fails, that reference is the only way to find the concrete or the steel in the building.

Piling records

Piles cannot be inspected once they are cast, so the pile record sheet is the evidence of what is in the ground. Fill it in at the rig for every pile, and test the piles as the Specification requires.

  • Pile reference, set-out coordinates and the position checked against the drawing
  • Platform level, cut-off level and the toe level reached, with the strata found while boring
  • Boring start and end times, casing length, and the support fluid where used
  • Reinforcement cage: length, bars and spacers, with its inspection
  • Concrete: theoretical and actual volumes, slump, cube references and placing times
  • Tests: integrity tests and load tests on the piles the Specification or the Engineer selects, with their results

An actual concrete volume below the theoretical volume can point to a narrowing of the pile shaft, so report it the same day and ask for an integrity test on that pile.

Blockwork, plaster and closing in

Walls and ceilings hide the services inside them. The rule is the same as for a slab: inspect what will be covered before it is covered.

  • Before blockwork: setting out, and wall starters and ties fixed to the structure
  • During blockwork: approved blocks and mortar, bond and full joints, plumb within the tolerance, lintels and movement joints
  • Before plaster: conduits, boxes and pipes in the walls inspected and tested, with beads and mesh at the junctions
  • Plaster: thickness and flatness, commonly within 3 mm under a 2 m straight edge, no cracks or hollow areas, and curing
  • Before the ceiling closes: services above tested and signed off, fire stopping complete, and an access panel for every valve and damper

When work fails: the NCR

Where work or materials do not meet the Specification, the Engineer may reject them by notice with reasons (Sub-Clause 7.5), and may instruct the Contractor to remove and replace them or to remedy them (7.6). A non-conformance report records the failure and how it is closed:

  1. 1What does not conform, where, and against which drawing or clause
  2. 2The immediate action: stop work in the area, and tag or set apart the materials
  3. 3The cause, so the same failure does not happen elsewhere
  4. 4The proposed disposition: rework, repair, replace, or use as it is with the Engineer’s acceptance
  5. 5Verification: the re-inspection or test that shows it is closed, signed by the Engineer
Sample wording
NCR-031. Level 3 slab, grids 2 to 4 and B to D. Cube set C-3-118 gave a 28-day average of 34.5 MPa against the specified cube strength of 40 MPa. The slab carries only its own weight. Proposed action: cores in the area to measure the strength in place, and a check of the slab design by the structural engineer. Work above this area is on hold until the results. The cause is under review with the concrete supplier.

Accepting work as it is changes what the Employer gets. Record the Engineer’s written acceptance, and agree any reduction in price, before the NCR is closed.

Common mistakes

  • Starting work before the inspection and test plan is accepted
  • Calling the Engineer before your own check, then failing the inspection
  • Covering or pouring before a hold point is released
  • Taking comments by word of mouth instead of on the signed request
  • Logging only the passes, which hides the true first-time pass rate
  • Losing the link between a test result and the element it came from
  • Closing an NCR without the re-inspection that proves it

Templates for each step

Inspection and test plan
Excel, 3 sheets
AED 99
AED 99
Inspection request and log
Excel, 4 sheets
AED 79
AED 49
AED 59
AED 39
AED 99
Pile integrity and static load test report templates
Word, 9 pagesExcel, 4 sheets
AED 79
AED 39
AED 39
AED 39
AED 39
Non-conformance report and log
Excel, 4 sheets
AED 79

More guides

All guides