Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

O&M manual structure and as-built index

AED 99
Launch offerAED 49.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
UAE practice
Time limit
Set by the agreement
Format
Word, 7 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 7. Handover and closeRoute: Both routes. Scope: Supply and install, Design, supply and install, Supply only, Services and supervision
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Section structure, system data sheets, maintenance schedules and the as-built drawing index reviewers expect.
  • Sent by the Main Contractor to the Engineer.
  • Written to UAE practice.

What you get

Save with a pack

Main Contractor to Engineer: Handover and close9 documents. Includes this document.
AED 622AED 399Save AED 223

Free basic version or the full version

Free

Basic version

  • The English Word form, 7 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 99

  • The same Word form, with no line in the footer
  • One-page guide on when and how to use it
  • Your logo and company details on every file
How to write it

How to put together an O&M manual

The operation and maintenance manual lets the Employer and the facilities team run, maintain and repair the building after handover. Under Sub-Clause 4.1 of the FIDIC 1999 Red Book, for any part the Contractor designed, the as-built documents and O&M manuals are submitted before the Tests on Completion, and that part is not complete for taking over until they are. Most specifications ask the same for every system.

What to include

  1. 1A master index and a building user guide, with the emergency contacts
  2. 2One volume per system, from architecture and structure to fire, electrical, building management and lifts
  3. 3For each system: its description, operation, planned maintenance, equipment data sheets and test records
  4. 4Warranties in the Employer’s name, the spare parts handed over and the special tools
  5. 5Health and safety: residual risks, hazardous materials and isolation points
  6. 6The as-built drawing index by discipline, with the drawings or the files

When to use it

Agree the structure early, collect the content system by system during installation and commissioning, and submit a draft for review well before completion. The final, reviewed copies go in before taking over.

Read the full guideHandover in construction: snag list, taking over and the defects period
Sample wording
Volume 3, Cooling and ventilation, Rev 1. Chapter 5, Equipment data: AHU-04, make and model as approved under MAR-118, serial number, location Level 2 plant room, rated airflow 6,500 l/s, supplier, and warranty expiry 30 November 2028. Manufacturer’s literature for the installed model only, with the model marked.

Common mistakes

  • Filling the manual with whole product catalogues instead of the installed models
  • Giving set points and schedules as designed, not as commissioned
  • Submitting it at the last minute, so taking over waits for the review

Questions people ask

What is the difference between the O&M manual and the as-built drawings?

The as-built drawings show what was built and where. The O&M manual explains how to run and maintain it. The manual carries the as-built drawing index, so the facilities team finds both in one place.

Who writes each volume?

The trade that installed the system writes its volume. The Contractor compiles and checks the whole manual and submits it with one index and one format.