Request for information form and register
What this document does
- Raises a question on drawings or specifications in a standard form and tracks every answer and its response time.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 1.9.
- Time limit: Response period set in the communication protocol, commonly 7 to 14 days.
What you get
- Fillable form
- Log with status and ageing
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write a request for information (RFI)
An RFI asks the Engineer or the designer to clarify drawings or specifications that are unclear, missing or in conflict. A clear question with the right references gets a fast answer, and a register shows which answers are late.
What to include
- 1An RFI number, the date and the discipline
- 2The drawing, specification section or bill item, with revisions
- 3One clear question, with a sketch or photograph where it helps
- 4Your proposed solution, if you have one
- 5The date the answer is needed for the work, linked to the programme
- 6The likely effect on cost or time if the answer changes the work
When to use it
As soon as the problem is found, early enough for the answer to arrive before the work. The response period is set in the communication protocol, commonly 7 to 14 days.
RFI 087, Structural. Drawing S-305 Rev B shows transfer beam TB-4 as 900 mm deep, while section 3 on drawing S-410 Rev A shows 750 mm. Please confirm the depth. The answer is needed by 18 June 2026 to keep the Level 4 slab pour on 25 June 2026.
Common mistakes
- Several questions in one RFI, so the answer comes back partial
- No date needed, so nobody knows it is urgent
- Treating an RFI as a notice: when the answer affects time or cost, give the notice the contract requires separately
Questions people ask
Is an RFI a notice under the contract?
No. When a late answer will delay or disrupt the work, give the Engineer a separate notice under Sub-Clause 1.9 of the FIDIC 1999 Red Book, and a notice of claim under Sub-Clause 20.1 if it causes delay or cost.
Who answers an RFI?
The Engineer, usually with the designer’s input. Under a design and build contract, many RFIs go to the Contractor’s own designer.