Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

Subcontractor and supplier approval request

AED 49
Launch offerAED 24.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 4.4
Time limit
Set by the agreement
Format
Word, 3 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 3. Sign and startRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

What you get

Save with a pack

Main Contractor to Engineer: Sign and start4 documents. Includes this document.
AED 296AED 189Save AED 107

Free basic version or the full version

Free

Basic version

  • The English Word form, 3 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 49

  • The same Word form, with no line in the footer
  • One-page guide on when and how to use it
  • Your logo and company details on every file
How to write it

How to ask for approval of a subcontractor

Under Sub-Clause 4.4 of the FIDIC 1999 Red Book the Contractor must not subcontract the whole of the Works, and needs the Engineer’s prior consent to each proposed Subcontractor, except suppliers of Materials alone and Subcontractors named in the Contract. The Contractor also gives the Engineer at least 28 days’ notice of the intended start of each Subcontractor’s work. Many specifications ask for approval of key suppliers too.

What to include

  1. 1The package and its scope, with the Specification sections
  2. 2The proposed subcontractor or supplier: trade licence, address and contact
  3. 3Similar projects completed, with references
  4. 4Key staff, resources and current workload
  5. 5Approvals the package needs, such as Civil Defence registration for fire systems
  6. 6The intended start of the work on site, at least 28 days after the notice

When to use it

Before you sign the subcontract, and at least 28 days before the subcontractor starts work. Ask early for long-lead packages, so a refusal does not hold up the programme.

Sample wording
Under Sub-Clause 4.4 we ask for your consent to appoint a fire protection subcontractor for the sprinkler, hydrant and fire pump works, Specification Section 21 13 13. The proposed company holds a valid trade licence and Civil Defence registration for fire protection systems, and has completed three similar residential towers in the last four years, listed in Attachment 2. We intend it to start work on site on 5 January 2027.

Common mistakes

  • Letting a subcontractor start on site before consent is given
  • Sending a name with no evidence of experience or approvals, so the request comes back
  • Assuming consent moves responsibility, when the Contractor stays responsible for the subcontractor’s work

Questions people ask

Can the Engineer refuse consent?

Yes, with reasons. Consent must not be unreasonably withheld or delayed (Sub-Clause 1.3), so a refusal should say what is missing.

Is a nominated subcontractor different?

Yes. The Employer or the Engineer chooses a nominated subcontractor under Clause 5. The Contractor may object by notice, with supporting details, as soon as practicable (Sub-Clause 5.2).