Main Contractor and Subcontractor

Subcontractor notice of delay and claim

SubcontractorMain Contractor
Clause
FIDIC Conditions of Subcontract 2011Sub-Clause 20.2
Time limit
Within 21 days of awareness, so the main contractor can notify within its own 28 days
Format
WordLanguage: English
Stage
Post-contract: 5. Changes and claimsRoute: Both routes

What this document does

  • Notifies delay or extra cost under the subcontract within the shorter time bar.
  • Sent by the Subcontractor to the Main Contractor.
  • Written to FIDIC Conditions of Subcontract 2011, Sub-Clause 20.2.
  • Time limit: Within 21 days of awareness, so the main contractor can notify within its own 28 days.
  • Goes with: Subcontract extension of time grant or rejection
  • Step 2 of 10 in the Delay and extension of time process.

What you get

Where it sits in the processes

Delay and extension of time, step 2 of 10View all
BeforeEarly warning notice
This documentSubcontractor notice of delay and claim
AfterNotice of claim