Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

Notice of claim

AED 59
Launch offerAED 29.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 20.1
Time limit
Not later than 28 days after awareness of the event, or the claim is lost
Format
Word, 4 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 5. Changes and claimsRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

Claim deadline calculatorEnter the date you became aware of the event and we email you 7 days before the notice and the fully detailed claim are due.

What this document does

What you get

Save with a pack

Main Contractor to Engineer: Changes and claims6 documents. Includes this document.
AED 654AED 429Save AED 225
Delay and extension of time process: Main Contractor steps4 documents. Includes this document.
AED 456AED 319Save AED 137

Free basic version or the full version

Free

Basic version

  • The English Word form, 4 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 59

  • The same Word form, with no line in the footer
  • One-page guide on when and how to use it
  • Your logo and company details on every file
How to write it

How to write a notice of claim

A notice of claim tells the Engineer that an event may entitle you to more time, more money or both. Under Sub-Clause 20.1 of the FIDIC 1999 Red Book it must be given within 28 days after you became aware, or should have become aware, of the event. The notice can be short: the detail follows in the claim.

What to include

  1. 1The contract name and number, and the parties
  2. 2The event, described in plain words, with its date
  3. 3The date you became aware of the event
  4. 4The Sub-Clauses you rely on, such as 8.4 for time and 1.9, 2.1 or 4.12 for the cause
  5. 5What you claim: an extension of time, additional payment, or both
  6. 6A statement that you are keeping contemporary records and will send the fully detailed claim
  7. 7The signature of your authorised representative, sent to the address and in the way the contract requires (Sub-Clause 1.3)

When to use it

Not later than 28 days after you became aware, or should have become aware, of the event. Send it even when the effect is not yet known. The fully detailed claim follows within 42 days, with interim claims every month while the effect continues.

Read the full guideHow to write a construction claim in the UAE
Sample wording
We give notice under Sub-Clauses 1.9 and 20.1 that the revised structural drawings for Level 3, which our notice of 2 February 2026 said were needed by 1 March 2026, were issued on 12 March 2026. The late drawings have delayed the concrete works and caused additional Cost. We became aware of the delay on 1 March 2026. We claim an extension of the Time for Completion under Sub-Clause 8.4 and payment of the Cost plus reasonable profit. We are keeping contemporary records and will send the fully detailed claim within 42 days.

Common mistakes

  • Waiting until the effect is known: the 28 days run from awareness, not from the end of the delay
  • Mentioning the event only in meeting minutes or a progress report instead of a separate notice
  • Leaving out the date you became aware of the event
  • Sending it to the wrong person or address instead of following Sub-Clause 1.3 and the notice address in the contract

Questions people ask

Is a notice of claim the same as the claim?

No. The notice keeps your right open. The fully detailed claim, with the analysis, the costs and the records, follows within 42 days, or within another period the Engineer approves.

What happens if the notice is late?

Under Sub-Clause 20.1, if notice is not given within 28 days, the Time for Completion is not extended, no additional payment is due and the Employer is discharged from liability for the claim. Treat the 28 days as a hard limit, and take advice if a notice was missed.

Can one notice cover several events?

It is safer not to. Give a separate notice for each event, so that each keeps its own 28 days and its own right to time and money.

What changes under FIDIC 2017?

The notice is still due within 28 days (Sub-Clause 20.2.1). The fully detailed claim is due within 84 days, and the notice lapses if the contractual or legal basis is not given in time (Sub-Clause 20.2.4).