Submittal review sheet with status code
What this document does
- The Engineer’s review with A, B, C or D status, numbered comments and the resubmission instruction.
- Sent by the Engineer to the Main Contractor.
- Written to FIDIC 1999 Red Book, Sub-Clause 7.2.
- Time limit: Review period per the contract, commonly 14 to 21 days.
- Goes with: Material approval request and submittal register
- Step 4 of 6 in the Material and shop drawing submittals process.
What you get
- Fillable form
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Word, 3 pages
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to review a submittal
The submittal review sheet records the Engineer’s or the design consultant’s review of a material, shop drawing or method statement submittal: the status code, each comment and what the Contractor must do next. Under Sub-Clause 3.1 of the FIDIC 1999 Red Book the review does not relieve the Contractor of its responsibility, so keep the comments clear and limited to compliance with the contract.
What to include
- 1The submittal number, revision, title and specification section
- 2The date received, and the date due under the review period
- 3The status code: A approved, B approved with comments, C revise and resubmit, D rejected
- 4Each comment numbered, with the clause or drawing it refers to
- 5What the Contractor must do next: proceed, proceed and follow the comments, or resubmit
- 6The reviewer’s name, discipline and date
When to use it
Within the review period the Specification sets, often 14 days for materials and longer for shop drawings. Return it on time even when the answer is C, so the Contractor can resubmit without losing the order date.
MAR-042 Rev 0, Section 09 30 00, porcelain floor tiles. Status B, approved with comments. 1. Colour light grey 2034 accepted as deviation D1, at no change in price. 2. Submit the slip resistance test for the wet-area tile before ordering it. 3. Grout colour to match the approved sample board. The Contractor may proceed with the order, subject to comments 2 and 3.
Common mistakes
- Returning a code C without saying exactly what is missing
- Commenting on preferences outside the Specification, which the Contractor can treat as an instruction
- Letting the review period run out, which delays the order and can lead to a claim
Questions people ask
What is the difference between B and C?
B means the Contractor may proceed and follow the comments. C means it must not order or install until a revised submittal is approved.
Can a review comment change the specification?
No. A comment that asks for more than the contract requires is a change, and should be instructed as a variation under Clause 13.