Engineer and Main Contractor

Submittal review sheet with status code

AED 49
Launch offerAED 24.50 on your first order, until 31 December.
EngineerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 7.2
Time limit
Review period per the contract, commonly 14 to 21 days
Format
Word, 3 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 4. Build and monitorRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

What you get

Save with a pack

Engineer to Main Contractor: Build and monitor7 documents. Includes this document.
AED 315AED 199Save AED 116
Material and shop drawing submittals process: Supervision Consultant steps2 documents. Includes this document.
AED 128AED 89Save AED 39
How to write it

How to review a submittal

The submittal review sheet records the Engineer’s or the design consultant’s review of a material, shop drawing or method statement submittal: the status code, each comment and what the Contractor must do next. Under Sub-Clause 3.1 of the FIDIC 1999 Red Book the review does not relieve the Contractor of its responsibility, so keep the comments clear and limited to compliance with the contract.

What to include

  1. 1The submittal number, revision, title and specification section
  2. 2The date received, and the date due under the review period
  3. 3The status code: A approved, B approved with comments, C revise and resubmit, D rejected
  4. 4Each comment numbered, with the clause or drawing it refers to
  5. 5What the Contractor must do next: proceed, proceed and follow the comments, or resubmit
  6. 6The reviewer’s name, discipline and date

When to use it

Within the review period the Specification sets, often 14 days for materials and longer for shop drawings. Return it on time even when the answer is C, so the Contractor can resubmit without losing the order date.

Read the full guideMaterial submittals in construction: the package, approval codes and samples
Sample wording
MAR-042 Rev 0, Section 09 30 00, porcelain floor tiles. Status B, approved with comments. 1. Colour light grey 2034 accepted as deviation D1, at no change in price. 2. Submit the slip resistance test for the wet-area tile before ordering it. 3. Grout colour to match the approved sample board. The Contractor may proceed with the order, subject to comments 2 and 3.

Common mistakes

  • Returning a code C without saying exactly what is missing
  • Commenting on preferences outside the Specification, which the Contractor can treat as an instruction
  • Letting the review period run out, which delays the order and can lead to a claim

Questions people ask

What is the difference between B and C?

B means the Contractor may proceed and follow the comments. C means it must not order or install until a revised submittal is approved.

Can a review comment change the specification?

No. A comment that asks for more than the contract requires is a change, and should be instructed as a variation under Clause 13.

Where it sits in the processes

Material and shop drawing submittals, step 4 of 6View all

Also used between