Material approval request and submittal register
What this document does
- Gets materials approved before they are ordered, with a register of what is pending, approved or rejected.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 7.2.
- Goes with: Submittal review sheet with status code
- Step 2 of 6 in the Material and shop drawing submittals process.
- Step 5 of 14 in the Specialist equipment procurement process.
What you get
- Fillable form
- Log with status and ageing
- Checklist of attachments
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write a material approval request
A material approval request, or material submittal, gets each material, product or system approved before it is ordered. Under Sub-Clause 7.2 of the FIDIC 1999 Red Book, samples and the relevant information are submitted for the Engineer’s consent before the materials are used in the Works.
What to include
- 1The request number and revision, the specification section and the item
- 2The manufacturer, the supplier and the country of origin
- 3Technical data sheets, test certificates and authority approvals, such as Civil Defence approval for fire-rated products
- 4A compliance statement against the specification, listing any deviation
- 5Samples, labelled with their origin and intended use in the Works
- 6The date approval is needed to place the order on time
When to use it
Before you place the order, allowing the review period in the specification. Resubmit with a new revision after every rejection or revise-and-resubmit code.
MAR 042 Rev 0, Section 09 30 00, Tiling. We submit porcelain floor tiles, 600 x 600 mm, slip rating R10, from the approved supplier list, with the data sheet, the test certificates and two samples. The product complies with the specification with no deviations. Approval is needed by 2 July 2026 to meet the delivery date for Level 2.
Common mistakes
- Ordering before approval, then replacing the material at your own cost
- Hiding deviations from the specification instead of listing them
- Missing certificates, which bring back a revise-and-resubmit code
Questions people ask
Does approval make the Engineer responsible for the material?
No. Under Sub-Clause 3.1 an approval does not relieve the Contractor of its responsibility. Order only against an approved code and follow the comments.
What do the status codes mean?
Most projects use A for approved, B for approved with comments, C for revise and resubmit, and D for rejected. Order against A or B, and follow the B comments.