Launch offer: 50% off your first order until 31 December. It comes off at checkout, no code needed.Launch offer: 50% off your first order

Engineer and Main Contractor

Taking-over certificate

AED 59
Launch offerAED 29.50 on your first order, until 31 December.
EngineerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 10.1
Time limit
Set by the agreement
Format
Word, 3 pagesEnglish and Arabic copy, 3 pages
Stage
Post-contract: 7. Handover and closeRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

What you get

Save with a pack

Engineer to Main Contractor: Handover and close6 documents. Includes this document.
AED 334AED 219Save AED 115
Handover, defects and close-out process: Supervision Consultant steps5 documents. Includes this document.
AED 285AED 199Save AED 86

Free basic version or the full version

Free

Basic version

  • The English Word form, 3 pages
  • No payment and no sign-up
  • A line in the footer: Free basic version from builderdraft.com
Download free
Full version

AED 59

  • The same Word form, with no line in the footer
  • English and Arabic copy, 3 pages
  • One-page guide on when and how to use it
  • Your logo and company details on every file
How to write it

How to issue a taking-over certificate

The taking-over certificate states the date the Works, or a Section, were completed and lists the minor work still outstanding. Under Sub-Clause 10.1 of the FIDIC 1999 Red Book the Contractor may apply up to 14 days before it expects completion, and the Engineer has 28 days to issue the certificate or reject the application with reasons.

What to include

  1. 1The contract, and the Works or Section taken over
  2. 2The date of completion in accordance with the contract
  3. 3Confirmation that the Tests on Completion have been passed
  4. 4The schedule of minor outstanding work and defects, with dates to finish them
  5. 5Documents still due, such as as-built drawings and manuals, if any
  6. 6The Engineer’s signature, with copies to the Employer and the Contractor

When to use it

Within 28 days after the Engineer receives the Contractor’s application. If the Engineer neither issues the certificate nor rejects the application with reasons, and the Works substantially comply with the contract, the certificate is deemed issued on the last day of that period.

Read the full guideHandover in construction: snag list, taking over and the defects period
Sample wording
In accordance with Sub-Clause 10.1, we certify that the Works were completed in accordance with the Contract on 30 September 2026, except for the minor outstanding work and defects listed in the attached schedule, which will not substantially affect the use of the Works for their intended purpose.

Common mistakes

  • A completion date left blank, or the date of signing used instead
  • Outstanding items with no dates to finish them
  • Letting the Employer use part of the Works without a certificate: under Sub-Clause 10.2 that part is deemed taken over

Questions people ask

What changes on taking over?

Care of the Works passes to the Employer (17.2), delay damages stop (8.7), the first half of the retention is released (14.9), the defects notification period starts (11.1), and the Contractor has 84 days to submit the Statement at completion (14.10).

Does the certificate end the Contractor’s obligations?

No. The Contractor still remedies defects notified in the defects notification period (Clause 11), and the Performance Certificate follows at its end (11.9).