Request for taking-over certificate
What this document does
- Applies for taking over with the completion evidence and the list of minor outstanding work.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 10.1.
- Time limit: Not earlier than 14 days before the works are expected to be complete; the Engineer responds within 28 days.
- Goes with: Taking-over certificate
- Step 5 of 14 in the Handover, defects and close-out process.
What you get
- Editable Word template
- Checklist of attachments
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Word, 4 pages
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
How to apply for the taking-over certificate
Under Sub-Clause 10.1 of the FIDIC 1999 Red Book the Contractor may apply, by notice to the Engineer, for a Taking-Over Certificate not earlier than 14 days before the Works will, in its opinion, be complete and ready for taking over. The Engineer then has 28 days to issue the certificate or reject the application with reasons. If the Engineer does neither and the Works substantially comply with the contract, the certificate is deemed issued on the last day of that period.
What to include
- 1A reference to Sub-Clause 10.1, and the Works or the Section applied for
- 2The date the Works will be complete and ready for taking over
- 3The Tests on Completion passed, with the reports
- 4The authority approvals obtained, such as the Civil Defence completion certificate
- 5The minor outstanding work and defects, in an attached list with completion dates
- 6The documents handed over, such as the O&M manuals and the as-built drawings
When to use it
Not earlier than 14 days before the date you expect the Works to be complete. Keep proof of the date the Engineer received the notice, because the 28 days run from receipt.
Under Sub-Clause 10.1 we apply for the Taking-Over Certificate for Section 2, Block B. In our opinion the Section will be complete and ready for taking over on 30 November 2026, 12 days after the date of this notice. The Tests on Completion were passed on 14 November 2026, the Civil Defence completion inspection on 17 November 2026, and the O&M manuals and as-built drawings were submitted on 10 November 2026. The minor outstanding items are listed in the attached snag list, with their completion dates.
Common mistakes
- Applying more than 14 days before completion, which the Engineer can treat as premature
- Leaving out the snag list, so the application is rejected for lack of detail
- Not recording the date of receipt, which the 28 days and deemed taking over depend on
Questions people ask
What if the Engineer does not reply?
If the Engineer neither issues the certificate nor rejects the application within 28 days, and the Works substantially comply with the contract, the certificate is deemed issued on the last day of that period (Sub-Clause 10.1).
Can the Engineer reject the application?
Yes, by notice with reasons, stating the work to be done first. Complete that work, then apply again with a new notice.