Variation register with estimates and approved values
What this document does
- Every potential and instructed variation with rough order estimate, proposal, recommended and approved values and status.
- Kept by the Engineer as its own record.
- Written to FIDIC 1999 Red Book, Sub-Clause 13.
- Step 6 of 10 in the Variation process.
What you get
- Excel register with automatic totals
- Dashboard page
- One-page guide on when and how to use it
- Worked example
- A full Arabic copy of every file, right to left
- File: Excel, 3 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to keep a variation register
The variation register tracks every change to the contract, from the day it is raised to its approved value. It shows your estimate, the contractor’s proposal, the Engineer’s recommendation and the approved value side by side, so you can see the forecast final cost and the allowance left at any time.
What to include
- 1A number, title, reason and date raised for every variation
- 2Who raised it, and the instruction or request it came from
- 3Your estimate, the contractor’s proposal and the Engineer’s recommendation
- 4The approved value, the variation order number and its date
- 5The status: potential, proposal requested, instructed, approved, rejected or withdrawn
- 6The effect on time, where an extension is claimed
- 7The forecast total, and the allowance left in the budget
When to use it
From the start of the contract to the final account. Log each variation on the day it is raised, before a proposal is asked for, and update it every time a proposal, a recommendation or an approval arrives.
VO-017, extra power outlets in the retail units, raised by the Employer on 14 April 2026. Estimate AED 182,000; proposal AED 236,500; Engineer’s recommendation AED 198,750; approved at AED 198,750 on 20 May 2026. No extension of time claimed.
Common mistakes
- Logging a variation only once it is approved
- Counting open items at zero in the forecast
- Leaving old items open: work started without approval becomes a claim
Questions people ask
How should open variations count in the forecast?
At the best figure you have: the Engineer’s recommendation, or else your estimate, or else the contractor’s proposal. Rejected and withdrawn items count as nothing.
Does the Engineer need the Employer’s approval to instruct?
Only if the Particular Conditions say so (Sub-Clause 3.1). Many UAE contracts set a value above which the Employer must approve first, so record that approval with the variation.