Variations in construction: request, proposal and variation order

A variation is a change to the Works instructed by the Engineer. Under the FIDIC 1999 Red Book it can be instructed at any time before the Taking-Over Certificate for the Works, either directly or after asking the contractor for a proposal (Sub-Clause 13.1).

6 min read FIDIC 1999 Red Book UAE and GCC

What counts as a variation

Sub-Clause 13.1 lists the changes a Variation may include:

  • Changes to the quantities of items in the Contract, although these are not always a Variation by themselves
  • Changes to the quality and other characteristics of any item of work
  • Changes to levels, positions or dimensions
  • Omission of work, unless it is to be carried out by others
  • Additional work, Plant, Materials or services
  • Changes to the sequence or timing of the Works

The routes to a variation

  1. 1
    The Engineer instructs

    A direct instruction under Sub-Clause 13.1. The Contractor carries out the work and the value is agreed or determined.

  2. 2
    The Engineer asks for a proposal

    Under Sub-Clause 13.3 the Contractor sends a description, a programme and a price, and the Engineer approves, disapproves or comments.

  3. 3
    The Contractor proposes

    A change the Contractor suggests, including value engineering (Sub-Clause 13.2).

  4. 4
    The Contractor asks for an instruction

    When a drawing or event changes the work without an instruction, a variation request asks the Engineer to confirm it.

How variations are valued

Work is valued at the contract rates where they apply. New rates apply where the work is not of a similar character or is not carried out under similar conditions, or where a quantity changes by more than 10% and the other tests in Sub-Clause 12.3 are met. Small or incidental work can be valued as daywork (Sub-Clause 13.6).

The time effect

A Variation is a ground for an extension of time under Sub-Clause 8.4. Record the time effect in the variation order. If it is left open, protect it with a notice under Sub-Clause 20.1.

Approvals in UAE practice

On many UAE projects the Particular Conditions require the Employer’s approval before the Engineer instructs a Variation above a set value (Sub-Clause 3.1). Check yours: an order issued without a required approval can be disputed later.

Sample wording
Under Sub-Clauses 13.1 and 13.3, please submit a proposal by 20 July 2026 for a steel canopy over the main entrance to drawing A-520 Rev A: a description of the work and a programme for it, any change to the Time for Completion, and your valuation. Do not start this work until a Variation is instructed.

Common mistakes

  • Starting changed work on a spoken instruction
  • Descriptions too vague to show what was included
  • Leaving the time effect open without a notice
  • Carrying out a change as normal work and claiming it months later