Variation proposal with cost and time breakdown
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 13.3
Time limit
As soon as practicable after the request; particular conditions often set 14 days
Format
Word and ExcelLanguage: English
Stage
Post-contract: 5. Changes and claimsRoute: Both routes
What this document does
- Description of the work, programme effect and a priced breakdown at contract rates or dayworks.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 13.3.
- Time limit: As soon as practicable after the request; particular conditions often set 14 days.
- Goes with: Variation order
- Step 5 of 10 in the Variation process.
What you get
- Editable Word template
- Excel schedules and summary sheet
- Worked example
- One-page guide on when and how to use it
- File: Word and Excel
- Language: English
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Where it sits in the processes
Variation, step 5 of 10View all
BeforeEngineer’s request for variation proposal
This documentVariation proposal with cost and time breakdown
AfterVariation register with estimates and approved values