Letter of award
What this document does
- Accepts the tender and records the price, time, securities and conditions agreed in negotiation.
- Sent by the Employer to the Design Consultant.
- Written to UAE practice.
- Step 13 of 14 in the Main contract tender and award process.
- Step 5 of 15 in the Design appointment and design development process.
What you get
- Editable Word template
- An English copy, and a copy with English and Arabic side by side
- Checklist of attachments
- File: Word, 4 pages
- File: English and Arabic copy, 4 pages
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
Free basic version or the full version
Basic version
- The English Word form, 4 pages
- No payment and no sign-up
- A line in the footer: Free basic version from builderdraft.com
AED 79
- The same Word form, with no line in the footer
- English and Arabic copy, 4 pages
- Your logo and company details on every file
How to write a letter of award
The letter of award, called the Letter of Acceptance in the FIDIC 1999 Red Book (Sub-Clause 1.1.1.3), accepts the tender and becomes one of the contract documents. It also starts several clocks, so it has to be exact.
What to include
- 1The tender accepted, with its date and reference
- 2The Accepted Contract Amount, with VAT shown separately
- 3The Time for Completion and the expected commencement
- 4The agreed clarifications and negotiated changes, as an annexed memorandum signed by both parties
- 5The securities and insurances to be provided, with their deadlines
- 6The documents forming the contract and their order of priority
- 7A request to acknowledge the award and to sign the Contract Agreement
When to use it
Before the tender validity expires. Then the Contractor provides the Performance Security within 28 days (Sub-Clause 4.2), the parties sign the Contract Agreement within 28 days (1.6), and the Commencement Date falls within 42 days unless the Particular Conditions say otherwise (8.1).
We accept your tender dated 12 August 2026 for the construction of the community centre, as clarified in the post-tender clarification letters annexed to this letter, for the Accepted Contract Amount of AED 24,860,000 excluding VAT. The Time for Completion is 540 days from the Commencement Date. Please provide the Performance Security within 28 days and confirm your acceptance by signing below.
Common mistakes
- Accepting the tender without the negotiated changes, which leaves the old terms in force
- No clear statement of whether the amount includes VAT
- Letting the tender validity lapse before the award
Questions people ask
What is the difference between a letter of award and a letter of intent?
A letter of award accepts the tender and becomes part of the contract. A letter of intent is used only when work must start before the contract is signed, with a cap on the cost and an expiry date.
Is the letter of award the contract?
It is one of the documents that make up the Contract under Sub-Clause 1.1.1.1 of the FIDIC 1999 Red Book, and the Contract Agreement follows within 28 days (Sub-Clause 1.6).