Fully detailed extension of time and prolongation claim

AED 249
Launch offerAED 124.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 20.1
Time limit
Within 42 days of awareness of the event
Format
Word, 8 pagesExcel, 7 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 5. Changes and claimsRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

Claim deadline calculatorEnter the date you became aware of the event and we email you 7 days before the notice and the fully detailed claim are due.

What this document does

  • Narrative, cause and effect, delay analysis table, prolongation cost build-up and supporting documents list.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 20.1.
  • Time limit: Within 42 days of awareness of the event.
  • Step 6 of 10 in the Delay and extension of time process.

What you get

Save with a pack

Main Contractor to Engineer: Changes and claims6 documents. Includes this document.
AED 654AED 429Save AED 225
Delay and extension of time process: Main Contractor steps4 documents. Includes this document.
AED 456AED 319Save AED 137
How to write it

How to write an extension of time claim

The fully detailed claim shows why you are entitled to more time and money, and how much. Under Sub-Clause 20.1 of the FIDIC 1999 Red Book it is due within 42 days after you became aware of the event, unless the Engineer approves another period. It builds on the notice of claim and the records you kept.

What to include

  1. 1A summary: the event, the Sub-Clauses relied on, and the time and money claimed
  2. 2The contractual basis: why the event entitles you under Sub-Clause 8.4 and the clause for its cause
  3. 3The facts in date order, each backed by a record such as a letter, an instruction, a site report or a photograph
  4. 4The delay analysis: the critical path before and after the event, on the accepted programme
  5. 5The extension claimed in days, and the new Time for Completion
  6. 6The prolongation cost for the delay period: site staff, facilities, plant and overheads, with the records behind each figure
  7. 7The list of supporting documents, and the records you will keep providing

When to use it

Within 42 days after you became aware of the event, or another period the Engineer approves. If the effect continues, send interim claims every month and a final claim within 28 days after the effect ends. The Engineer responds within 42 days with approval, or disapproval and detailed comments.

Read the full guideHow to claim an extension of time (EOT) under FIDIC
Sample wording
This is our fully detailed claim under Sub-Clause 20.1 for the delay caused by the late issue of the Level 3 structural drawings, notified on 20 March 2026. The delay to the critical path is 34 days, shown in the time impact analysis in Appendix B against Programme Revision 4. We claim an extension of the Time for Completion of 34 days under Sub-Clause 8.4 and prolongation costs of AED 612,400, built up in Appendix C.

Common mistakes

  • Claiming the whole period of the event without showing its effect on the critical path
  • A global claim that does not link each cost to the event
  • Ignoring your own delays and concurrent delays instead of dealing with them in the analysis
  • Missing the 42 days, or stopping the monthly interim claims while the effect continues

Questions people ask

Which delay analysis method should I use?

Use the one the contract requires. If it says nothing, a time impact analysis on the accepted programme is the most common while the work is in progress. A method the Engineer can follow and check matters more than its name.

Can I claim profit on prolongation?

Only where the Sub-Clause you rely on allows Cost plus reasonable profit, such as 1.9 (late drawings) or 2.1 (late access to the Site) in the 1999 Red Book. Others, such as 4.12 (unforeseeable physical conditions), allow Cost only.

What changes under FIDIC 2017?

The entitlement moves to Sub-Clause 8.5, and the fully detailed claim is due within 84 days after awareness instead of 42 (Sub-Clause 20.2.4). Concurrent delay follows the rules in the Special Provisions.

Where it sits in the processes

Delay and extension of time, step 6 of 10View all
BeforeContemporary records pack and delay event log
This documentFully detailed extension of time and prolongation claim
AfterEngineer’s determination