Fully detailed extension of time and prolongation claim
What this document does
- Narrative, cause and effect, delay analysis table, prolongation cost build-up and supporting documents list.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 20.1.
- Time limit: Within 42 days of awareness of the event.
- Step 6 of 10 in the Delay and extension of time process.
What you get
- Editable Word template
- Excel schedules and summary sheet
- Worked example
- Checklist of attachments
- A full Arabic copy of every file, right to left
- File: Word, 8 pages
- File: Excel, 7 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write an extension of time claim
The fully detailed claim shows why you are entitled to more time and money, and how much. Under Sub-Clause 20.1 of the FIDIC 1999 Red Book it is due within 42 days after you became aware of the event, unless the Engineer approves another period. It builds on the notice of claim and the records you kept.
What to include
- 1A summary: the event, the Sub-Clauses relied on, and the time and money claimed
- 2The contractual basis: why the event entitles you under Sub-Clause 8.4 and the clause for its cause
- 3The facts in date order, each backed by a record such as a letter, an instruction, a site report or a photograph
- 4The delay analysis: the critical path before and after the event, on the accepted programme
- 5The extension claimed in days, and the new Time for Completion
- 6The prolongation cost for the delay period: site staff, facilities, plant and overheads, with the records behind each figure
- 7The list of supporting documents, and the records you will keep providing
When to use it
Within 42 days after you became aware of the event, or another period the Engineer approves. If the effect continues, send interim claims every month and a final claim within 28 days after the effect ends. The Engineer responds within 42 days with approval, or disapproval and detailed comments.
This is our fully detailed claim under Sub-Clause 20.1 for the delay caused by the late issue of the Level 3 structural drawings, notified on 20 March 2026. The delay to the critical path is 34 days, shown in the time impact analysis in Appendix B against Programme Revision 4. We claim an extension of the Time for Completion of 34 days under Sub-Clause 8.4 and prolongation costs of AED 612,400, built up in Appendix C.
Common mistakes
- Claiming the whole period of the event without showing its effect on the critical path
- A global claim that does not link each cost to the event
- Ignoring your own delays and concurrent delays instead of dealing with them in the analysis
- Missing the 42 days, or stopping the monthly interim claims while the effect continues
Questions people ask
Which delay analysis method should I use?
Use the one the contract requires. If it says nothing, a time impact analysis on the accepted programme is the most common while the work is in progress. A method the Engineer can follow and check matters more than its name.
Can I claim profit on prolongation?
Only where the Sub-Clause you rely on allows Cost plus reasonable profit, such as 1.9 (late drawings) or 2.1 (late access to the Site) in the 1999 Red Book. Others, such as 4.12 (unforeseeable physical conditions), allow Cost only.
What changes under FIDIC 2017?
The entitlement moves to Sub-Clause 8.5, and the fully detailed claim is due within 84 days after awareness instead of 42 (Sub-Clause 20.2.4). Concurrent delay follows the rules in the Special Provisions.