Notice of variation and request for instruction

AED 49
Launch offerAED 24.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 13.1
Time limit
Promptly after identifying the change; particular conditions often set 7 days
Format
Word, 3 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 5. Changes and claimsRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

Claim deadline calculatorEnter the date you became aware of the event and we email you 7 days before the notice and the fully detailed claim are due.

What this document does

  • Notifies that an instruction or event constitutes a variation and asks the Engineer to confirm or instruct.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 13.1.
  • Time limit: Promptly after identifying the change; particular conditions often set 7 days.
  • Step 3 of 10 in the Variation process.

What you get

Save with a pack

Main Contractor to Engineer: Changes and claims6 documents. Includes this document.
AED 654AED 429Save AED 225
Variation process: Main Contractor steps3 documents. Includes this document.
AED 207AED 139Save AED 68
How to write it

How to write a variation request

When an instruction, a revised drawing or an event changes the work but was not issued as a Variation, tell the Engineer in writing and ask for it to be confirmed or instructed. Under the FIDIC 1999 Red Book Variations are made by the Engineer’s instruction (Sub-Clause 13.1), so a change without one can go unpaid.

What to include

  1. 1The instruction, drawing or event, with its reference and date
  2. 2What changed against the contract documents: drawings, specification or bill of quantities item
  3. 3Why it is a Variation and not part of the original scope
  4. 4The likely effect on cost and time
  5. 5A request to confirm or instruct the Variation by a date
  6. 6A reservation of your right to claim under Sub-Clause 20.1 if it is not instructed

When to use it

Promptly, as soon as you identify the change and before the changed work starts. Your Particular Conditions may set a period for this. If the Engineer does not instruct a Variation, give a notice of claim within 28 days after you became aware of the event.

Read the full guideVariations in construction: request, proposal and variation order
Sample wording
Drawing M-210 Rev D, received on 4 May 2026, adds ten fan coil units on Level 5 that are not shown on the contract drawings or in the bill of quantities. We consider this a Variation under Sub-Clause 13.1 and ask for your instruction by 11 May 2026. The likely addition is AED 145,000 and about 12 days on the mechanical works. We reserve our rights under Sub-Clause 20.1.

Common mistakes

  • Carrying out the changed work as normal work and claiming it months later
  • Relying on a spoken instruction given at a site meeting
  • Not keeping records of the changed work from the first day

Questions people ask

Is this the same as a variation proposal?

No. This letter asks the Engineer to recognise and instruct a change. A variation proposal under Sub-Clause 13.3 is the Contractor’s description, programme and price for a change, sent when the Engineer asks for one.

Do I still need a notice of claim?

Yes, if the Engineer does not instruct a Variation. Give notice under Sub-Clause 20.1 within 28 days after you became aware of the event to keep your right to time and money.

Where it sits in the processes

Variation, step 3 of 10View all
BeforeSubcontract variation request
This documentNotice of variation and request for instruction
AfterEngineer’s request for variation proposal