Notice of variation and request for instruction
What this document does
- Notifies that an instruction or event constitutes a variation and asks the Engineer to confirm or instruct.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 13.1.
- Time limit: Promptly after identifying the change; particular conditions often set 7 days.
- Step 3 of 10 in the Variation process.
What you get
- Editable Word template
- One-page guide on when and how to use it
- Time-limit reminder table
- A full Arabic copy of every file, right to left
- File: Word, 3 pages
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to write a variation request
When an instruction, a revised drawing or an event changes the work but was not issued as a Variation, tell the Engineer in writing and ask for it to be confirmed or instructed. Under the FIDIC 1999 Red Book Variations are made by the Engineer’s instruction (Sub-Clause 13.1), so a change without one can go unpaid.
What to include
- 1The instruction, drawing or event, with its reference and date
- 2What changed against the contract documents: drawings, specification or bill of quantities item
- 3Why it is a Variation and not part of the original scope
- 4The likely effect on cost and time
- 5A request to confirm or instruct the Variation by a date
- 6A reservation of your right to claim under Sub-Clause 20.1 if it is not instructed
When to use it
Promptly, as soon as you identify the change and before the changed work starts. Your Particular Conditions may set a period for this. If the Engineer does not instruct a Variation, give a notice of claim within 28 days after you became aware of the event.
Drawing M-210 Rev D, received on 4 May 2026, adds ten fan coil units on Level 5 that are not shown on the contract drawings or in the bill of quantities. We consider this a Variation under Sub-Clause 13.1 and ask for your instruction by 11 May 2026. The likely addition is AED 145,000 and about 12 days on the mechanical works. We reserve our rights under Sub-Clause 20.1.
Common mistakes
- Carrying out the changed work as normal work and claiming it months later
- Relying on a spoken instruction given at a site meeting
- Not keeping records of the changed work from the first day
Questions people ask
Is this the same as a variation proposal?
No. This letter asks the Engineer to recognise and instruct a change. A variation proposal under Sub-Clause 13.3 is the Contractor’s description, programme and price for a change, sent when the Engineer asks for one.
Do I still need a notice of claim?
Yes, if the Engineer does not instruct a Variation. Give notice under Sub-Clause 20.1 within 28 days after you became aware of the event to keep your right to time and money.