Engineer and Main Contractor

Review notice and no-objection letter

EngineerMain Contractor
Clause
FIDIC 1999 Yellow BookSub-Clause 5.2
Time limit
Within the 21-day review period; with no notice, the document is deemed approved
Format
WordLanguage: English and Arabic
Stage
Post-contract: 4. Build and monitorRoute: Design and Build

What this document does

  • The Engineer’s notice of no objection, or of the respects in which the document fails to comply, without relieving the contractor of responsibility.
  • Sent by the Engineer to the Main Contractor.
  • Written to FIDIC 1999 Yellow Book, Sub-Clause 5.2.
  • Time limit: Within the 21-day review period; with no notice, the document is deemed approved.
  • Goes with: Contractor’s Documents submission (design submission)
  • Step 5 of 8 in the Design submissions under Design and Build process.
  • For Design and Build projects only.