Engineer and Main Contractor

Snag list and joint inspection record

AED 59
Launch offerAED 29.50 on your first order, until 31 December.
EngineerMain Contractor
Clause
FIDIC 1999 Red BookSub-Clause 10.1
Time limit
Set by the agreement
Format
Excel, 4 sheetsLanguage: English, plus a full Arabic copy
Stage
Post-contract: 7. Handover and closeRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Items by location with photographs, responsibility, target date and sign-off.
  • Sent by the Engineer to the Main Contractor.
  • Written to FIDIC 1999 Red Book, Sub-Clause 10.1.
  • Step 6 of 14 in the Handover, defects and close-out process.

What you get

Save with a pack

Engineer to Main Contractor: Handover and close6 documents. Includes this document.
AED 334AED 219Save AED 115
Handover, defects and close-out process: Supervision Consultant steps5 documents. Includes this document.
AED 285AED 199Save AED 86
How to write it

How to prepare a snag list

A snag list records every defect and unfinished item found before handover, by location, with who will fix it and by when. Closing the important items allows taking over under Sub-Clause 10.1, and minor items are finished in the defects notification period.

What to include

  1. 1A snag reference and the location: building, level, room or area
  2. 2A description and a photograph number
  3. 3The discipline and the party responsible
  4. 4The priority: A before taking over, B in the defects period
  5. 5The target date, the completion date and the Engineer’s check
  6. 6A joint inspection record with signatures

When to use it

From the first pre-handover inspections, usually four to six weeks before completion, until every snag is closed, including those in the defects notification period.

Read the full guideHandover in construction: snag list, taking over and the defects period
Sample wording
SN-0142, Tower A, Level 7, Apartment 704, kitchen. Chipped edge on the worktop next to the sink, photograph 0142. Responsible: the joinery subcontractor. Priority B. Target date: 30 October 2026.

Common mistakes

  • Vague locations that nobody can find again
  • Closing snags on the contractor’s word without the Engineer’s check
  • Mixing major defects with minor items, which delays taking over

Questions people ask

Can the Works be taken over with snags still open?

Yes, if the outstanding work and defects will not substantially affect the use of the Works. Under Sub-Clause 10.1 they are listed with the Taking-Over Certificate and finished in the defects notification period.

Who closes a snag?

The contractor fixes it and marks it ready for checking. Only the Engineer’s check on site closes it.