Snag list and joint inspection record
What this document does
- Items by location with photographs, responsibility, target date and sign-off.
- Sent by the Engineer to the Main Contractor.
- Written to FIDIC 1999 Red Book, Sub-Clause 10.1.
- Step 6 of 14 in the Handover, defects and close-out process.
What you get
- Excel register with automatic totals
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
How to prepare a snag list
A snag list records every defect and unfinished item found before handover, by location, with who will fix it and by when. Closing the important items allows taking over under Sub-Clause 10.1, and minor items are finished in the defects notification period.
What to include
- 1A snag reference and the location: building, level, room or area
- 2A description and a photograph number
- 3The discipline and the party responsible
- 4The priority: A before taking over, B in the defects period
- 5The target date, the completion date and the Engineer’s check
- 6A joint inspection record with signatures
When to use it
From the first pre-handover inspections, usually four to six weeks before completion, until every snag is closed, including those in the defects notification period.
SN-0142, Tower A, Level 7, Apartment 704, kitchen. Chipped edge on the worktop next to the sink, photograph 0142. Responsible: the joinery subcontractor. Priority B. Target date: 30 October 2026.
Common mistakes
- Vague locations that nobody can find again
- Closing snags on the contractor’s word without the Engineer’s check
- Mixing major defects with minor items, which delays taking over
Questions people ask
Can the Works be taken over with snags still open?
Yes, if the outstanding work and defects will not substantially affect the use of the Works. Under Sub-Clause 10.1 they are listed with the Taking-Over Certificate and finished in the defects notification period.
Who closes a snag?
The contractor fixes it and marks it ready for checking. Only the Engineer’s check on site closes it.