The time limits
The Engineer then agrees or determines the extension of time and the additional payment under Sub-Clause 3.5. Your Particular Conditions may change any of these periods, so check them first.
Step 1: the notice of claim
The notice only has to describe the event and say that you claim. Keep it short and send it on time: the detail follows in the claim. Include:
- The contract name and number, and the parties
- The event, in plain words, with its date
- The date you became aware of it
- The Sub-Clauses you rely on
- What you claim: an extension of time, additional payment, or both
- A statement that you are keeping contemporary records
We give notice under Sub-Clause 20.1 that the Employer has not yet given us access to Zone C of the Site, which was due on 1 April 2026 under Sub-Clause 2.1. We became aware of the delay on 1 April 2026. We claim an extension of the Time for Completion and payment of the Cost plus reasonable profit. We are keeping contemporary records and will send the fully detailed claim within 42 days.
Step 2: the fully detailed claim
The fully detailed claim proves the entitlement and the amount. It should let the Engineer check every figure without asking for more:
- 1A summary of the event, the Sub-Clauses relied on, and the time and money claimed
- 2The contractual basis for each part of the claim
- 3The facts in date order, each with a record behind it
- 4The delay analysis on the accepted programme, showing the effect on the critical path
- 5The cost build-up, with the records behind each figure
- 6The list of supporting documents
Records that win claims
Under Sub-Clause 20.1 the Engineer may inspect the records you keep, and a claim is only as strong as its records. Start them on the day of the event:
- Daily site reports signed by both sides
- Programme updates and look-aheads
- Letters, instructions and RFIs, with the dates they were sent and received
- Photographs with dates and locations
- Cost records: timesheets, plant logs, invoices and hire records
Common mistakes
- Waiting until the effect is known before giving notice
- Raising the event only in meeting minutes or progress reports
- A global claim that does not link each cost to the event
- Stopping the monthly interim claims while the effect continues
UAE law and your contract
FIDIC-based contracts are also common in Saudi Arabia, Qatar, Oman, Kuwait and Bahrain, often with local Particular Conditions. The steps are the same, and the periods and the governing law follow your contract. In the UAE, the new Civil Transactions Law, Federal Decree-Law No. 25 of 2025, took effect on 1 June 2026 and replaced the 1985 Civil Code; it generally does not apply to contracts made before that date. For a dispute or a missed deadline, take legal advice.