Engineer and Main Contractor

Request for performance certificate

AED 39
Launch offerAED 19.50 on your first order, until 31 December.
Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 11.9
Time limit
Set by the agreement
Format
Word, 3 pagesLanguage: English, plus a full Arabic copy
Stage
Post-contract: 7. Handover and closeRoute: Both routes
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Applies for the certificate once all defects are remedied and the period has expired.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 11.9.
  • Goes with: Performance certificate
  • Step 12 of 14 in the Handover, defects and close-out process.

What you get

Save with a pack

Main Contractor to Engineer: Handover and close9 documents. Includes this document.
AED 622AED 399Save AED 223
Handover, defects and close-out process: Main Contractor steps6 documents. Includes this document.
AED 495AED 349Save AED 146
How to write it

How to ask for the performance certificate

The Performance Certificate is the only certificate that constitutes acceptance of the Works (Sub-Clause 11.9 of the FIDIC 1999 Red Book). The Engineer issues it within 28 days after the latest expiry date of the defects notification periods, or as soon after that as the Contractor has supplied all its documents and completed and tested all the Works, including remedying any defects. A request letter shows that all of that is done.

What to include

  1. 1A reference to Sub-Clause 11.9, and the expiry date of each defects notification period
  2. 2Confirmation that every notified defect is remedied, with the closed defects register
  3. 3The Contractor’s Documents supplied, such as the final as-built drawings and manuals
  4. 4Any test or work still outstanding, with its date
  5. 5A request to return the Performance Security and release the rest of the retention
  6. 6The date you will submit the draft final statement

When to use it

Shortly before the last defects notification period expires, so the Engineer can check the work in time to issue the certificate within 28 days after the expiry.

Read the full guideHandover in construction: snag list, taking over and the defects period
Sample wording
The defects notification period for the Works expires on 15 December 2026. All 46 defects notified under Sub-Clause 11.1 have been remedied and closed by the Engineer, as listed in the attached register, and the final as-built drawings were resubmitted on 1 December 2026. Under Sub-Clause 11.9 we ask you to issue the Performance Certificate within 28 days after that date.

Common mistakes

  • Waiting for the Engineer instead of asking, while the Performance Security stays open
  • Leaving defects open on the register, which delays the certificate
  • Forgetting the 56 days to submit the draft final statement after the certificate (Sub-Clause 14.11)

Questions people ask

What happens after the certificate?

The Employer returns the Performance Security within 21 days after receiving a copy of the certificate (Sub-Clause 4.2). The Contractor submits a draft final statement within 56 days (14.11), then the discharge (14.12).

When is the rest of the retention paid?

When the latest defects notification period has expired, the Engineer certifies the outstanding retention for payment (Sub-Clause 14.9). Where the Works were taken over in Sections, each Section’s share follows its own period.

Where it sits in the processes

Handover, defects and close-out, step 12 of 14View all
BeforeDefect notification and log
This documentRequest for performance certificate
AfterPerformance certificate