Engineer and Main Contractor

Testing and commissioning method statement and report

Main ContractorEngineer
Clause
FIDIC 1999 Red BookSub-Clause 9.1
Time limit
Set by the agreement
Format
Word and ExcelLanguage: English
Stage
Post-contract: 7. Handover and closeRoute: Both routes. Scope: Supply and install, Install only, Design, supply and install, Services and supervision
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

What this document does

  • Pre-commissioning checks, test procedures, witness points and result sheets by system.
  • Sent by the Main Contractor to the Engineer.
  • Written to FIDIC 1999 Red Book, Sub-Clause 9.1.
  • Step 3 of 14 in the Handover, defects and close-out process.

What you get

Where it sits in the processes

Handover, defects and close-out, step 3 of 14View all

Also used between