Testing and commissioning method statement and report
What this document does
- Pre-commissioning checks, test procedures, witness points and result sheets by system.
- Sent by the Main Contractor to the Engineer.
- Written to FIDIC 1999 Red Book, Sub-Clause 9.1.
- Step 3 of 14 in the Handover, defects and close-out process.
What you get
- Editable Word template
- Excel schedules and summary sheet
- Checklist of attachments
- One-page guide on when and how to use it
- A full Arabic copy of every file, right to left
- File: Word, 11 pages
- File: Excel, 4 sheets
- Language: English, plus a full Arabic copy
- Brand-ready: your logo and company details go in when you download
- Pay once and use it on every project
Save with a pack
Free basic version or the full version
Basic version
- The English Word form, 11 pages
- No payment and no sign-up
- A line in the footer: Free basic version from builderdraft.com
AED 129
- The same Word form, with no line in the footer
- Excel, 4 sheets
- One-page guide on when and how to use it
- Your logo and company details on every file
How to plan and report testing and commissioning
Testing and commissioning proves that each system works as designed before the Works are taken over. The method statement plans the checks and tests system by system, and the report records the results. Under Sub-Clause 9.1 of the FIDIC 1999 Red Book, the Contractor gives at least 21 days’ notice of the date it will be ready for each Test on Completion.
What to include
- 1The systems to be tested, and the order they are tested in
- 2The checks before commissioning: installation complete, cleaned, flushed and powered
- 3The procedure, acceptance criteria and instruments for each test
- 4The witness points for the Engineer, the authority and the client
- 5The notice date and the test date for each test
- 6The results, and the signed result sheets
- 7Failed tests, and the retest that closes each one
When to use it
Before the Tests on Completion start, and after the documents in Sub-Clause 4.1(d) are submitted for the parts the Contractor designed. Give at least 21 days’ notice of readiness; the tests are then carried out within 14 days after that date unless agreed otherwise, and a certified report of the results follows.
Under Sub-Clause 9.1 we give notice that the chilled water system for Building B will be ready for the Tests on Completion after 15 August 2026. The tests follow method statement TC-HVAC-03 Rev 2: flow balancing, pump performance and a 72-hour run, witnessed by the Engineer.
Common mistakes
- Starting tests before the pre-commissioning checks are complete
- Giving less than 21 days’ notice
- Leaving the authority witness tests to the end, when they are hardest to book
- Closing a failed test without a recorded retest
Questions people ask
When is the test report due?
As soon as the Works, or a Section, pass a test, the Contractor submits a certified report of the results to the Engineer (Sub-Clause 9.1).
What if the Contractor delays the tests?
The Engineer may give notice requiring the tests within 21 days. If the Contractor still does not test, the Employer’s Personnel may carry them out at the Contractor’s risk and cost (Sub-Clause 9.2).