Processes

Variation

From a change found on site to a signed variation order, and back down into the subcontract.

Show steps for
10 steps in this process
Procurement routeApplies to the Employer, consultants and Main Contractor

The Employer designs through its consultant, tenders complete drawings and bills, and the contractor builds. FIDIC 1999 Red Book.

EmployerSupervision ConsultantMain ContractorSubcontractorSupplierSupplier quotation with compliance statementSupplier quotationwith compliancestatement1Subcontract variation requestSubcontract variationrequest2Notice of variation and request for instructionNotice of variationand request forinstruction3Engineer’s request for variation proposalEngineer’s requestfor variationproposal4Variation proposal with cost and time breakdownVariation proposalwith cost and timebreakdown5Variation register with estimates and approved valuesVariation registerwith estimates andapproved values6Engineer’s recommendation to the Employer (variation)Engineer’srecommendation to theEmployer (variation)7Variation approval formVariation approvalform8Variation orderVariation order9Subcontract variation orderSubcontract variationorder10
1Supplier quotation with compliance statement
SupplierSubcontractor
AED 59
2Subcontract variation request
SubcontractorMain Contractor
SC 13
AED 49
3Notice of variation and request for instruction
Main ContractorEngineer
RB 13.1 Promptly after identifying the change; particular conditions often set 7 days
AED 49
4Engineer’s request for variation proposal
EngineerMain Contractor
RB 13.3
AED 39
5Variation proposal with cost and time breakdown
Main ContractorEngineer
RB 13.3 As soon as practicable after the request; particular conditions often set 14 days
AED 99
6Variation register with estimates and approved values
Engineer, internal step
RB 13
AED 149
7Engineer’s recommendation to the Employer (variation)
Supervision ConsultantEmployer
RB 13.3
AED 79
8Variation approval form
Employer, internal step
AED 49
9Variation order
EngineerMain Contractor
RB 13.3
AED 79
10Subcontract variation order
Main ContractorSubcontractor
SC 13
AED 59

All steps: Variation process