Guide

The new UAE Civil Transactions Law: what changes for construction contracts

Since 1 June 2026, a new Civil Transactions Law has governed contracts in the UAE, replacing the law of 1985. Its chapter on the contract for work, Articles 812 to 839, sits behind every construction contract, FIDIC ones included. This guide goes through the rules that matter on site and in the office, article by article, with what to do differently and sample wording.

10 min read Federal Decree-Law No. 25 of 2025 UAE and GCC
A contracts manager and a project engineer reviewing a construction contract and drawings in a site office

Key dates and time limits

1 June 2026The new law in force, replacing Federal Law No. 5 of 1985 (Federal Decree-Law No. 25 of 2025, Articles 2 and 3)
Before 1 June 2026The law does not apply to earlier facts and dealings unless it says otherwise (Article 4), so contracts made before then generally stay under the 1985 law
ImmediatelyThe contractor’s notice of defects in materials the employer supplied, or of anything that may impede the work (Article 816(3))
A reasonable periodThe time the employer sets in a notice to correct defective work, before ending the contract or bringing in another contractor (Article 818(2))
10 yearsJoint liability of the contractor and the engineer for collapse and serious defects, counted from handover (Articles 821 and 822)
3 yearsThe time to bring a claim under that liability, from the collapse or the discovery of the defect (Article 824)

A FIDIC contract still sets most of the rules between the parties. The law fills the gaps where the contract is silent, and a few of its rules apply whatever the contract says. Under Sub-Clause 1.4 of the FIDIC 1999 Red Book the contract is governed by the law named in the Appendix to Tender, which on UAE projects is UAE law.

The rules at a glance

The contract for work, Articles 812 to 839, and the general rules most used on construction projects
TopicArticleThe rule
Notice of impediments816(3)Notify the employer immediately, or bear every consequence of not doing so
Defective work818(2) and (3)Notice to correct within a reasonable period, then termination or completion by others at the contractor’s cost
Unit-rate overrun828Notify the expected increase over the estimate, or lose the right to recover it
Lump-sum price829(1) and (2)No increase for higher material or labour prices; changes paid only if the employer caused or authorised them and agreed the price
Exceptional events829(3) and 224The court may extend time, raise or lower the price, or end the contract
Ten-year liability821 to 824Contractor and engineer jointly liable for 10 years from handover; cannot be excluded or limited
Subcontracting832 and 833Allowed unless the contract forbids it; the main contractor stays liable
Handover and payment825 to 827The employer must take over completed work, and pays on handover unless agreed otherwise
Termination for convenience836The employer may stop the work at any time, paying costs, work done and lost profit
Delay damages340The court may reduce them; more only for fraud or gross fault

Notice of anything that may hold up the work

Article 816(3) is the rule most likely to change daily practice. If defects appear in materials the employer supplied, or any other factor arises that may impede the work, the contractor must notify the employer immediately. If it neglects to, it is responsible for all the consequences of that neglect. Law firms commenting on the new law note that the 1985 law had no express duty like this.

FIDIC already asks for notices: Sub-Clause 8.3 for probable future events, 1.9 for late drawings and 20.1 within 28 days for claims. The law adds a plainer standard. Waiting until day 27 of the 28 may still meet the contract, but it can leave the contractor bearing consequences the law places on late notice. Give a short notice as soon as the problem is known, and the detailed claim later.

Sample wording
Under Article 816(3) of the Civil Transactions Law and Sub-Clauses 1.9 and 8.3 of the Contract, we notify you that the facade bracket shop drawings, submitted for review on 2 November 2026, have not been returned. Facade installation on Levels 8 to 12 is due to start on 1 December 2026 and will be held up if the drawings are not returned by 24 November 2026. If delay or extra cost results, we will give notice of claim under Sub-Clause 20.1.

Send the notice to the person and address the contract names, keep proof of the time it was received, and log it in the correspondence register. A notice nobody can find later has little value.

Defective work: notice, correction and termination

If it becomes clear during the work that the contractor is working defectively or against the contract, the employer may give notice to comply and correct the work within a reasonable period it sets. If that period passes without correction, the employer may, after establishing the facts, end the contract or give the work to another contractor at the first contractor’s cost (Article 818(2)).

Article 818(3) lets the employer ask to end the contract at once, with no period to correct, where:

  • Fixing the defects is impossible or would go against the contract
  • The contractor is so late in starting or finishing that it cannot possibly complete in the agreed time
  • The contractor’s conduct shows it does not intend to perform
  • The contractor has done something that makes performance impossible

Commentators differ on whether 818(3) needs a court or tribunal decision, so take advice before relying on it. For employers, “after establishing the facts” is the key phrase: record the defect with a joint inspection, photographs and a non-conformance report before acting. FIDIC’s own route is the notice to correct under Sub-Clause 15.1 and remedial work under 7.6.

Sample wording
Under Sub-Clause 15.1 of the Contract and Article 818(2) of the Civil Transactions Law, you are required to correct the defective waterproofing to the Level 1 podium, grids 3 to 9, recorded in NCR-044 and the joint inspection of 16 November 2026, by 30 November 2026. If the work is not corrected by that date, the Employer may have it carried out by others at your cost.

Delay damages: what Article 340 allows

Parties may agree the damages in advance, as FIDIC does with delay damages under Sub-Clause 8.7. Under the 1985 law (Article 390) a court could adjust agreed damages up or down to match the actual loss. Article 340 now works mostly one way:

  • The court may reduce agreed damages if the debtor proves they are exaggerated, or that part of the obligation was performed
  • It may reduce them, or award nothing, where the creditor’s own fault caused or increased the loss
  • The creditor may claim more than the agreed amount only by proving fraud or gross fault
  • Any agreement against these rules is void

For contractors, records of the employer’s delays, late instructions and late approvals now support both an extension of time and a reduction of delay damages. For employers, set the daily rate as a genuine estimate of the loss, and keep the working that supports it.

Price rises and exceptional events

Article 829(1) is blunt. Where the work is done to an agreed design for a lump sum, the contractor cannot claim more because material prices, wages or other costs rose. Changes to the design are paid only if they are due to the employer’s fault, or the employer authorised them and agreed the extra price with the contractor (Article 829(2)). On a remeasured contract, Article 828 needs the contractor to notify the employer, with the expected increase, when the work will exceed the estimated quantities, or lose the right to recover the excess.

The relief is for exceptional events. If general exceptional circumstances that could not be foreseen when the contract was made break the balance between the parties’ obligations, and the financial basis of the contract gives way, the court may restore the balance: extend the time, raise or lower the price, or end the contract (Article 829(3)). The general rule in Article 224 lets the court reduce an obligation that has become oppressive, or end the contract, and any agreement to the contrary is void.

The surest protection against price rises is in the contract itself: a price adjustment clause such as Sub-Clause 13.8 of FIDIC 1999, or provisional sums for volatile items. Agree the price of every change in writing before the work starts.

Ten-year liability

  • Where the engineer designs a building or fixed structure and the contractor builds it under the engineer’s supervision, both are jointly liable for 10 years for total or partial collapse, even if it comes from a defect in the ground or the employer allowed the defective work (Article 821(1))
  • The liability covers defects that threaten the strength and safety of the building (821(2)), and the 10 years run from handover to the employer (821(3))
  • An engineer who only designed is liable for design defects; one who only supervised is jointly liable for the execution defects under its supervision (Article 822)
  • Any term that excludes or limits this liability is void (Article 823)
  • A claim must be brought within 3 years of the collapse or the discovery of the defect (Article 824)
  • The rule does not govern the contractor’s own recourse against its subcontractors (821(4)), so that depends on the subcontract

Main contractors should give their subcontracts their own 10-year warranty and indemnity for structural work, and keep as-built records, test results and approvals for the whole period.

Subcontracting

A contractor may subcontract all or part of the work unless the contract forbids it or the nature of the work needs the contractor to do it personally, and it stays liable to the employer for the subcontractor (Article 832). A subcontractor cannot claim from the employer what the main contractor is owed, unless the main contractor has assigned that right to the subcontractor (Article 833). Under FIDIC, the Engineer’s consent under Sub-Clause 4.4 is still needed.

Handover and payment

  • The employer must take over completed work once the contractor places it at its disposal. If it refuses without lawful reason after formal notice, the contractor is not liable if the work is then damaged without its fault (Article 825)
  • The price is due on handover unless agreed otherwise (Article 826); FIDIC replaces this with interim payments under Clause 14
  • Where the work is in parts or priced by the unit, the contractor is paid for each distinct part after inspection and acceptance (Article 827)

Ending the contract early

The employer may withdraw from the contract and stop the work at any time before completion. It must compensate the contractor for its expenses, the work done and what it could have earned by finishing; the court may reduce the lost profit where fair, and must deduct what the contractor saved or earned elsewhere (Article 836). FIDIC 1999 Sub-Clause 15.5 sets its own terms for termination for convenience, paying under Sub-Clause 19.6 without lost profit, so compare the two before either side acts. Either party may also ask to end the contract where an excuse prevents performance (Article 835).

Negotiations and tenders

Negotiations must be started, conducted and broken off in good faith. Negotiating does not oblige anyone to sign, but a party that negotiates or walks away in bad faith pays the other side’s actual loss, and deliberately hiding a material fact counts as bad faith (Article 121). Each side must also disclose information of decisive importance to the other’s consent (Article 122). Keep tender clarifications and negotiation records in writing.

Rules a contract cannot change

Most of the chapter applies only where the contract is silent. These rules say any agreement to the contrary is void:

  • The court’s power to reduce an oppressive obligation or end the contract in exceptional circumstances (Article 224)
  • The court’s power to reduce agreed damages, and the limit on claiming more (Article 340)
  • The ten-year liability of the contractor and the engineer (Article 823)

Common mistakes

  • Waiting for the end of the 28-day claim period before telling the employer about a problem already known
  • Signing a lump-sum contract with no price adjustment clause and expecting the law to cover price rises
  • Starting a change before its price is agreed in writing
  • Ending a contract for defects without first recording the facts
  • Relying on a clause that limits the ten-year liability
  • Subcontracting structural work without a subcontract warranty

This guide explains the law in general terms. For a live dispute or a large contract, take advice from a UAE lawyer on the contract itself.

Templates for each step

Early warning notice
Word, 4 pages
AED 39
Notice of claim
Word, 4 pages
AED 59
Correspondence and notices register
Excel, 5 sheets
AED 59
Notice to correct
Word, 3 pagesEnglish and Arabic copy, 3 pages
AED 49
Defect notification and log
Word, 4 pagesExcel, 3 sheets
AED 59
Delay damages notice and calculation
Word, 4 pagesExcel, 7 sheets
AED 79
AED 49
Suspension and termination notice set
Word, 11 pagesEnglish and Arabic copy, 11 pages
AED 149
Request for taking-over certificate
Word, 4 pages
Collateral warranty to the Employer
Word, 6 pagesEnglish and Arabic copy, 7 pages
AED 199
Subcontract agreement, supply and installation
Word, 10 pagesEnglish and Arabic copy, 14 pages
AED 399
Final account statement and agreement
Excel, 8 sheets
AED 199